r/AustralianDataCentres • • Mar 05 '26

Mapping the Top Data Centres in Australia

5 Upvotes

Australia has about 1.6GW of data centre capacity operating, on DC Byte figures in Mandala Partners’ August 2026 study for Data Centres Australia. Mandala forecasts deployable capacity reaching 3,100MW by 2030, up from 1,350MW in 2024, and CBRE puts the supply gap at 0.7 to 1.7GW by 2028. We’ve mapped where that capacity sits and where the next wave is going. Some things that stand out:

Sydney is still the centre of gravity, but the biggest proposals are now outside the capitals. Syncline Energy’s Plumpton precinct in Victoria is at 2.4GW in its latest public plans. Zerra DC’s Western Downs campus at Kogan in Queensland is 1.44GW in its August 2026 application, and CDC’s Wagga Wagga campus in New South Wales runs to 1.4GW. Each would come close to or exceed everything operating nationally today.

Anthropic has become the market’s biggest new buyer. It went to tender for at least 1.4GW of Australian capacity. The AFR reported its first lease at the Kogan campus on 16 September, and advanced talks to anchor AirTrunk’s 540MW Kurri Kurri campus in the Hunter on 22 September. On 16 October the AFR reported that Anthropic is the customer behind DigiCo’s 71MW contract at SYD1 in Sydney.

OpenAI is the other anchor in play. NEXTDC’s S7 at Eastern Creek is planned with OpenAI under a December 2025 MOU, valued at about A$7bn and now 612MW in its planning documents. It is going through the NSW planning process.

The established operators keep building. CDC’s 504MW Marsden Park campus won NSW approval in November 2025, and its 150MW Laverton campus in Melbourne has been under construction since early 2025. NEXTDC’s 162MW M4 at Fishermans Bend was approved in January 2026. Alongside them, neoclouds such as Sharon AI, Firmus and IREN are building GPU-first capacity.

SUBCO’s SMAP hypercable reached ready for service on 25 June 2026, linking Sydney, Melbourne, Adelaide and Perth with more than 400Tbps of capacity. A Tasmanian branch built with Firmus is due in the second quarter of 2027.

On the government side, 62 sites now hold the Hosting Certification Framework’s top Certified Strategic rating, run by 14 providers. Sydney has 25, Canberra 15 and Melbourne 9. NEXTDC ($NXT) is the only operator certified in every mainland capital plus Darwin. Tasmania has none.

Full market overview: https://certifiedstrategic.com/insights/top-data-centres-in-australia-2026-directory-and-market-overview

Interactive maps of Sydney, Melbourne, Queensland and Western Australia: https://certifiedstrategic.com/maps

Full directory: https://certifiedstrategic.com/sites

Which region do you expect to add the most operating megawatts by 2028: Western Sydney, western Melbourne, or one of the regional gigawatt sites?

Happy to answer questions on the certification framework, specific operators or the connectivity picture.


r/AustralianDataCentres • • 5h ago

NVIDIA halts AI server shipments to Malaysia, Singapore, Thailand and Indonesia, FT reports

1 Upvotes

NVIDIA has told the companies that build servers around its chips to stop shipping them to Malaysia, Singapore, Thailand and Indonesia, the Financial Times reported on 26 November, citing three people with knowledge of the matter. Server makers including Dell and Supermicro have told buyers in those countries that NVIDIA will not let their orders ship. The company declined to comment, and the FT's sources said it is unclear whether the halt is temporary.

Full story: https://certifiedstrategic.com/insights/nvidia-halts-ai-server-shipments-southeast-asia-malaysia-singapore

The halt follows a US rule, in force since 19 November, that requires a licence for advanced AI chips going to those four countries and Brazil. Chips are exempt when the company receiving or using them is headquartered in the United States, provided the exporter reports to Washington every month.

A second part of the rule applies in every country. Data centres renting large amounts of computing to companies headquartered in China need a licence for their chips by 17 February 2027.

TikTok owner ByteDance is one of those companies headquartered in China. The FT reports that some lenders have stopped about US$500 million of credit for NVIDIA chips that Singapore cloud company Aolani planned to run in Malaysia for it.

Those four markets include campuses built by three Australian-founded operators. AirTrunk, NEXTDC and Firmus have built or committed capacity in Malaysia, Singapore and Indonesia, while servers bound for Australia need no country licence.


r/AustralianDataCentres • • 17h ago

ByteDance plans $15bn Victorian data centre, report says

2 Upvotes

Property publication Green Street News has reported that TikTok owner ByteDance is preparing to build a $15 billion data centre in regional Victoria, which would be its first in Australia.

Full story: https://certifiedstrategic.com/insights/bytedance-tiktok-15bn-data-centre-regional-victoria

The reported figure is smaller than TikTok's commitments in Thailand and Brazil. Thailand's Board of Investment approved a TikTok expansion worth 842 billion baht, about US$25 billion, in May 2026, and TikTok announced a Brazilian campus at the Pecém port in December 2025, with estimated investment of more than R$200 billion.

The report follows an earlier attempt. The Australian Financial Review reported on 1 December 2025 that a TikTok plan for a 100MW campus in NSW or Victoria had gone more than a year without foreign investment approval. According to the AFR, TikTok asked Australian operators for construction proposals in 2025.

Foreign investment approval can cover long leases as well as land purchases. Under the Foreign Acquisitions and Takeovers Act, a lease likely to run more than five years, including extensions, counts as an interest in Australian land, and the Treasurer decides applications on the Foreign Investment Review Board's advice.

ByteDance already works with an Australian operator in Asia. It partnered with Sydney-headquartered AirTrunk in Singapore's 2023 data centre pilot.

Back in Victoria, the report lands as the state votes on 28 November, with nine data centre applications worth about A$5 billion waiting for the next state government.


r/AustralianDataCentres • • 3d ago

NVIDIA reinstates Jensen Huang as CEO 11 days after he resigned

13 Upvotes

NVIDIA has reinstated Jensen Huang as president and chief executive, effective immediately, and returned him to its board. The board's vote was unanimous, and it was announced on 23 November, US time.

Full story: https://certifiedstrategic.com/insights/jensen-huang-reinstated-nvidia-ceo-australia

Shares in NVIDIA rose about 30 per cent in early New York trading on the news, CNBC and CBS News reported. Huang resigned on 12 November after reports of extramarital affairs, including one with a former executive of Singapore cloud company Megaspeed. US intelligence agencies suspected her of spying for China, CBS News reported, and China has denied it.

In its statement, the board said meetings with Huang had satisfied it about his candour and his ability to lead the company. It took input from senior levels of the US government, and on that basis is confident his return carries no national security risk.

Colette Kress, who ran the company as interim chief executive, stays on as chief financial officer. The decision reverses the board's position of 17 November. On that day's results call, board chair Harvey Jones said the board "does not intend to reinstate Jensen as CEO". Support for Huang kept growing over the following week.

The "Stand with Jensen" petition passed 200,000 signatures, Business Insider reported, and President Donald Trump wrote on 22 November that he hoped the board would rehire him. Treasury Secretary Scott Bessent had called on 15 November for an outside chief executive. On CBS's Face the Nation on 22 November, he said: "I said they should go to the outside, but he's on the outside now."

Bessent's 10-day deadline for answers on export compliance runs to about 25 November, US time. Inside NVIDIA, a committee of independent directors is investigating reports that Huang was the target of a foreign intelligence effort, and the board said he supports that investigation. A new board committee now oversees export compliance, and NVIDIA is searching for a chief compliance officer.

Before his reinstatement, Huang agreed to transcribed interviews with congressional committees on 1 December, the Associated Press reported.

In Australia, Huang returns to deals NVIDIA made while he ran the company. It owns shares in Firmus and takes a share of Sharon AI's cloud revenue on 72MW here. With IREN, it holds a warrant to buy up to 30 million shares for US$2.1 billion. Those three are among the eight Australian partners in NVIDIA's plan for up to 2GW of AI factories, with NEXTDC, AirTrunk and CDC Data Centres among the others.


r/AustralianDataCentres • • 2d ago

Melbourne leads Asia Pacific data centre leasing with 1,546MW as Victorian approvals slow

2 Upvotes

Melbourne leased more data centre capacity than any other Asia Pacific market in the first nine months of 2026, according to datacenterHawk's third-quarter report. Customers took 1,546MW in Melbourne to 30 September, ahead of 1,279MW in Johor, 973MW in Jakarta and 710MW in Sydney.

Full story: https://certifiedstrategic.com/insights/melbourne-tops-asia-pacific-data-centre-leasing-victoria-election

Most of that leasing came in the September quarter, when customers took 1,370MW in Melbourne. That one quarter was more than every European market combined, and more than twice the city's total for all of 2025. Across Asia Pacific, 94 per cent of leasing to 30 September was preleased, signed before the capacity was built.

Donny Gunadi, datacenterHawk's senior insight analyst for Asia Pacific, told W.Media that "we are not seeing signs of speculative over-ordering in Australia". That demand arrived while Victorian approvals slowed. Hume and Melton councils called for a moratorium in August, and Jemena suspended parts of the power works for NEXTDC's M3 campus in West Footscray in September. Monash City Council refused Centuria's 38MW Clayton data centre on 29 September, and NEXTDC has kept M4 and M5 on hold until they have customer contracts.

Over the same weeks, HyperDC's application for a Moorabool campus, north-west of Geelong, was received on 22 September. On 9 November, AirTrunk set out its plans for a campus at Mickleham, with an A$26.5 million community package subject to approvals. Victoria entered the caretaker period on 3 November, and nine data centre applications, including Stockland's 250MVA Brooklyn campus, have been held over until after the 28 November vote. The planning minister in the government formed after it will decide them, and Centuria can ask the state tribunal to review the Clayton refusal.


r/AustralianDataCentres • • 5d ago

Austrade pitches data centres to nine UK pension funds holding A$4 trillion

5 Upvotes

Nine of the UK's largest pension funds, holding about A$4 trillion between them, are in Australia looking for private-market deals, the Australian Financial Review reported. Australia's trade agency, Austrade, is promoting data centres and digital infrastructure to them, along with defence, critical minerals, social housing and decarbonisation.

Full story: https://certifiedstrategic.com/insights/uk-pension-funds-australia-data-centres-mansion-house-accord

The delegation includes Aviva, Legal & General, Nest, Pension Insurance Corporation, People's Partnership, Rothesay, Standard Life and the Universities Superannuation Scheme. All eight belong to the Sterling 20, a partnership of the UK's largest pension providers and insurers.

Their room to invest here comes from the Mansion House Accord, signed in May 2025. Two of the visiting funds already back data centres in the UK. Legal & General holds a stake in operator Kao Data, and in 2025 it launched a digital infrastructure fund with about €600 million in first-close commitments. The Universities Superannuation Scheme has committed up to £250 million to Blackstone's planned 720MW campus at Cambois in Northumberland.

On the same trip, the delegation met Treasurer Jim Chalmers at a roundtable focused on energy, critical minerals and digital infrastructure.


r/AustralianDataCentres • • 5d ago

Oxford Economics ranks Australia fastest-growing of 25 data centre construction markets to 2028

5 Upvotes

Australia will be the fastest-growing of 25 data centre construction markets through to 2028, economic consultancy Oxford Economics forecasts in a briefing dated 12 November. Ireland is second, coming off a much smaller base.

Full story: https://certifiedstrategic.com/insights/oxford-economics-data-centre-construction-australia-fastest-growing

The consultancy counts more than A$250 billion in proposed Australian data centre projects and expects A$50 billion of them to proceed. It bases its near-term forecasts on projects under construction and projects it judges highly likely to go ahead, because announcements far exceed what the construction industry can deliver.

Its Australian team puts data centre construction work at about A$5.3 billion in FY26. It expects that to peak in FY29 at about A$14 billion in 2023/24 prices, when data centres would become Australia's largest non-residential building sector.

The Australian Bureau of Statistics has already reported data centre construction growing for an eighth straight quarter, and NEXTDC builder Kapitol expects a company record for data centre starts. For that build-out, Oxford Economics says tight construction labour markets limit how many projects can break ground.

Power availability to expected to increasingly shape where data centres are built. Beyond Australia, the consultancy expects construction across all 25 markets to grow 20 per cent in 2027 and 11 per cent in 2028, then peak in 2030 at US$212 billion in 2023 prices. The United States accounts for more than 60 per cent of the growth over the next two years. After 2030, it expects construction to fall 40 per cent by 2037 as growth in AI adoption slows. That would leave activity at three times its 2022 level.


r/AustralianDataCentres • • 6d ago

Four Sydney data centre plans withdrawn in six weeks

45 Upvotes

Four data centre plans in Sydney have been withdrawn before approval within six weeks, three of them in one business park at Lane Cove West.

Full story: https://certifiedstrategic.com/insights/sydney-data-centre-plans-dropped-lane-cove-cooks-river

Goodman withdrew the first, its 90MW, A$1.2 billion Project Mars at 12 Mars Road, on 28 September. The company said the policy and regulatory environment for large-scale data centre development had "evolved significantly".

A second proposal, at 16-20 Mars Road, left the NSW fast-track in October before it was lodged. Landholder Aurora Property Partnership cited commercial reasons. AirTrunk confirmed on 6 November that it will not build a 140MW data centre on the same street. A spokesperson said the site's "steep terrain and limited scale" made it unsuitable, and that the company is focusing on Kurri Kurri in NSW and Mickleham in Melbourne's north.

The fourth plan was at Arncliffe, where Stockland and John Boyd Properties took a data centre out of their masterplan for the former Kogarah Golf Club. Stockland called it a market-led decision, and the site is now planned as a logistics precinct.

In Western Sydney over the same period, CDC Data Centres expanded its Kemps Creek plan from one building to six, rated at about 1.4GW at peak. Microsoft won approval for a 96MW data centre at Huntingwood on 1 October.

The four withdrawals are unlikely to change the industry's forecast for Sydney, which Data Centres Australia and DC Byte kept at 2.0GW of capacity by 2030 in their 30 October report.NSW is now finalising grid rules that charge data centres an entry bond of A$30,000 a megawatt when they apply to connect.

Its August consultation paper proposed a default upgrade fee of A$200,000 a megawatt in Sydney. For a 140MW Sydney application, that would mean a A$4.2 million bond and, at the default rate, an upgrade fee of up to A$28 million. The regulations are due by 19 December.


r/AustralianDataCentres • • 6d ago

Stockland plans A$5bn, 365MW AI data centre campus at Kemps Creek with EdgeConneX

2 Upvotes

Stockland plans a A$5 billion data centre campus on Aldington Road at Kemps Creek, in Western Sydney, with its joint venture partner EdgeConneX. Its environmental impact statement has been open for public comment since 19 November.

Full story: https://certifiedstrategic.com/insights/stockland-aldington-road-kemps-creek-data-centre-365mw

The plan sets out two buildings with 33 data halls on a 30.5-hectare site in the Mamre Road industrial precinct, at a maximum IT load of 365MW. The company's quarterly update of 19 October lists its 50 per cent Kemps Creek interest with a target customer of "AI/Hyperscaler".

Those halls are designed for both air-cooled and higher-density liquid-cooled computing. Power would come straight from Transgrid's 330kV network through a new Ropes Creek switching station and a substation of up to 1,000MVA on the site, with 500MVA allocated to the data centre.

That substation would serve a campus whose maximum power consumption is 444MW, according to the exhibition notice, up from the 245MW of total power covered by the study requirements issued in April. That campus would take 44 months to build, and the work would support about 1,375 full-time equivalent jobs, according to the cost report.

The EIS expects operations to start in 2029, with about 84 staff running the campus. Public comment closes on 17 December 2026. The Minister for Planning and Public Spaces or the Independent Planning Commission then decides.


r/AustralianDataCentres • • 6d ago

NEXTDC lifts FY27 EBITDA guidance to A$260m to A$275m and explores a joint venture for S4 Sydney

3 Upvotes

NEXTDC raised its FY27 guidance on 20 November, before its annual general meeting, a month after a delay to grid power at its M3 campus in Melbourne forced it to cut its forecasts. It now expects underlying EBITDA of A$260 million to A$275 million, up from A$245 million to A$265 million. The bottom of its net revenue range rose by A$10 million, to A$485 million to A$500 million.

Full story: https://certifiedstrategic.com/insights/nextdc-fy27-guidance-upgrade-agm-s4-joint-venture

Both ranges still leave out the M3 contracts affected by the delay. The company put the higher EBITDA range down to cost savings and higher expected net revenue, and reaffirmed capital expenditure guidance of A$4.5 billion to A$5 billion.

That capital expenditure is mostly committed to contracted capacity, and NEXTDC's forward order book stands at about 565MW. S4 at Horsley Park in western Sydney is the largest contracted development, with customers signed for 250MW of the planned 365MW IT load. "We continue to explore capital recycling opportunities, including a joint venture structure for our S4 Sydney campus," NEXTDC said, and it does not expect to raise capital from shareholders to deliver its current contracted capacity.

At M3, NEXTDC and Jemena are working on alternative power routes, including through industrial streets and underground, alternative substations and feeder upgrades. Jemena has told NEXTDC that it does not expect to recommence the suspended works before February 2027.

Also at the AGM, proxies show 72.03 per cent of votes against the remuneration report, a second strike that puts a conditional spill resolution to the vote. Proxies lodged before the meeting show 95.75 per cent of votes against the spill itself.


r/AustralianDataCentres • • 7d ago

Sydney data centers cancelling projects

37 Upvotes

Work for a sydney power company, there have been about 10 data center projects from 60-200MW cancel their projects in the last 2 months. Some were at advanced stages of planning with power capacity secured and hundreds of thousands in sunk connection costs. Feel there will be some consolidation in the market and a general slow down in data center builds. The gov new rules around power and water appear to be having a large impact along with debt financing.


r/AustralianDataCentres • • 7d ago

Tasmania's lower house votes for a moratorium on new AI data centres

7 Upvotes

Tasmania's House of Assembly has passed a Greens motion calling for an immediate moratorium on new AI and data centres larger than 5MW. The pause would stay until parliament agrees new legislation and regulation is in place. The vote was 17 to 13, with the Greens, Labor and six independents for it, and the Liberals and the Shooters, Fishers and Farmers against.

Full story: https://certifiedstrategic.com/insights/tasmania-ai-data-centre-moratorium-motion

The motion asks the government to act, and the decision stays with the government. Business, Industry and Resources Minister Felix Ellis told parliament in August that the government would not seek a moratorium, and on 13 November it released its final expectations for data centre developers.

Those expectations ask every data centre above 20MW to pay at least A$3,000 a year into a community fund for each megawatt it contracts. Developers are also expected to contract new Tasmanian generation and report energy and water use every quarter.

Labor wants those obligations set in law before projects go ahead, and its votes carried the motion. In September the party had joined the Liberals to vote down a Greens moratorium.

That moratorium could now come through a bill from Franklin independent Peter George, which sets a pause in law. The bill also allows data centres only in designated zones, with public consultation and appeal rights kept. This needs to pass both the House of Assembly and the Legislative Council.

Both the motion and the bill concern a pipeline that could need up to about 1,150MW. Firmus expects to contract about 444MW across its three northern Tasmanian sites, and a government document lists six further unnamed proposals of up to 705MW.


r/AustralianDataCentres • • 7d ago

Macquarie Data Centres files plans for a A$2bn, 200MW Macquarie Park campus

1 Upvotes

Macquarie Data Centres has filed plans for a 200MW data centre campus at 2 Alma Road, Macquarie Park, in Sydney's north. Its scoping report, dated 27 October 2026, estimates the development cost at approximately A$2 billion.

Full story: https://certifiedstrategic.com/insights/macquarie-engineering-technology-campus-macquarie-park

The report asks the NSW planning department to set the studies the company must complete before the project opens for public comment. The project is listed on the state's planning portal as the Macquarie Engineering and Technology Campus.

That campus pairs two data centre buildings of generally five to six storeys with a teaching, training and research facility delivered in partnership with Macquarie University. The second stage adds Alma Park, a 4,495 square metre public park on the Alma Road frontage.

A grid connection was one of the steps parent company Macquarie Technology Group listed when it took up its option over the land in July. Ausgrid has since confirmed a 132kV connection is appropriate for the campus's maximum demand of about 350MVA to 400MVA. Its proposed Wallumatta switching station is the preferred supply.

The report expects first load on that connection in late 2029. The new campus adds to the company's existing Macquarie Park campus on Talavera Road, which reaches 65MW once its SuperWest building is fully built. Further along Talavera Road, Goodman's Project Apollo was approved on 2 September 2026 with a 135MW power cap.

The company says it will address the state's August 2026 data centre guidelines in its environmental impact statement, the next step after the department sets its requirements.


r/AustralianDataCentres • • 8d ago

NVIDIA's results name Australia's planned 2GW AI buildout as revenue hits US$115.8bn

3 Upvotes

NVIDIA has just reported its third-quarter results. Revenue rose 103 per cent to US$115.8 billion in the three months to 25 October, and data centre revenue rose 110 per cent to US$107.6 billion. The company expects about US$130 billion in the quarter to January, assuming no data centre compute revenue from China.

Full story: https://certifiedstrategic.com/insights/nvidia-q3-fy27-results-australia-2gw-dsx-ai-factories

Its data centre highlights include its collaboration with Australian partners "on infrastructure supporting a planned buildout of up to 2 gigawatts by 2027". Australia is the only country named in those highlights. On the results call, interim chief executive Colette Kress set the date for that capacity at the end of calendar 2027.

The buildout was announced in September with eight partners: Firmus, Sharon AI, IREN, Megaport, ResetData, CDC, NEXTDC and AirTrunk. Since then, CDC has lodged plans for a campus of up to 1.4GW at Wagga Wagga, and IREN has proposed its 900MW Redbank campus nearby. AirTrunk raised a A$4.25 billion loan to keep building SYD3 in Western Sydney, and Megaport signed three AI computing contracts worth A$978.6 million.

The results were NVIDIA's first since Jensen Huang resigned as chief executive on 12 November. Board chair Harvey Jones said the board "does not intend to reinstate Jensen as CEO" and had hired Heidrick & Struggles to find a permanent chief executive.


r/AustralianDataCentres • • 8d ago

Chalmers' super test change could open funding for AI data centre power

2 Upvotes

Treasurer Jim Chalmers has announced a change to the annual super performance test. Funds will be able to have up to 5 per cent of their portfolios judged against inflation plus a margin, instead of against market indices.

Full story: https://certifiedstrategic.com/insights/chalmers-super-performance-test-reset-ai-power

That change could help fund new power for AI data centres, because the indices track new energy projects poorly. Some AI data centre operators are signing power deals linked to new wind, solar and battery projects that still need construction capital. Super funds have mostly stayed out of building them: Market Forces found over 96 per cent of the A$771 million Australia's 30 largest funds put directly into renewable energy and battery storage since 2020 went to buying existing assets or companies.

One of those power deals is in South Australia, where Gunvor has a 12-year agreement to supply 600MW of firm electricity to Firmus's planned AI campuses at Tailem Bend and Stirling North. Gunvor will support 1.2GW of new renewable generation and 1.5GWh of battery storage by 2032.

That kind of project is typically measured against the Australian Unlisted Infrastructure benchmark under the current test, and that benchmark is mainly power, airports and other transport.

ASFA's submission lists data centres, and energy transition assets including generation, storage and transmission, among the assets its proposed eligibility rules would likely cover. Data centres are already in super portfolios, mostly as stakes in operating businesses.

Commonwealth Superannuation Corporation held 12.04 per cent of CDC after its February 2025 sale, and AustralianSuper has put A$4.7 billion into Vantage Data Centers EMEA and DataBank. For new AI campuses, the eligibility criteria, which are still to be set, will decide whether construction counts.Whatever the criteria say, the new benchmark is expected from the 2028-29 test and will apply only to new investments. ASFA welcomed the reforms, while the Coalition and One Nation have positioned against them, the ABC reported.


r/AustralianDataCentres • • 9d ago

US requires licences for AI chips going to Singapore, Malaysia, Indonesia, Thailand and Brazil

3 Upvotes

The US Commerce Department has moved to stop Chinese companies renting American AI chips in data centres outside China. Its new rule, released on 16 November, US time, sets two licence requirements for advanced AI chips.

Full story: https://certifiedstrategic.com/insights/us-ai-chip-licences-singapore-malaysia-australia-remote-access

US export controls have long covered where chips are shipped. That left a Chinese company barred from buying NVIDIA's Blackwell chips largely free to rent them in a data centre in another country. The Financial Times reported in November 2025 that Alibaba and ByteDance were training models in Southeast Asian data centres leased from non-Chinese operators.

Under the first requirement, any data centre in the world will need a US licence for its chips if it rents large amounts of computing to Chinese companies. That covers companies headquartered in China and Macau, and in the other countries under US arms embargoes. TechCrunch puts the threshold at about the computing power of 750 NVIDIA H100 chips. Data centres already serving those customers will have 90 days to get a licence.

The second requirement applies to advanced AI chips shipped to Singapore, Malaysia, Indonesia, Thailand and Brazil, which Washington rates as higher-risk countries. Each shipment will need a licence, reviewed case by case. Chips for US-headquartered companies are exempt, provided the exporter reports to Washington every month.

The four Asian countries have large data centre build pipelines. JPMorgan's July note puts planned data centre capacity through 2030 at 12.7GW in Malaysia, 5.8GW in Indonesia, 5.1GW in Thailand and 1.7GW in Singapore. Robert Walker, an economist at Sydney's Lowy Institute, told Bloomberg the curbs "would pose a major headwind to data centre investments in those countries".

Australian-founded operators are among those building there. AirTrunk says its four campuses in Johor, Malaysia, will carry more than 700MW of IT load, and NEXTDC opened KL1 in Kuala Lumpur in May. Firmus is co-developing a 360MW AI factory in Batam, Indonesia, with Singapore's DayOne.

Australia is not among the five, so those same neoclouds need no new licence for chips going into Australian data centres. That holds as long as their customers are not headquartered in China, Macau or another arms-embargoed country.

Both requirements start on the day the rule appears in the US Federal Register, and the Commerce Secretary can add more countries to the five.


r/AustralianDataCentres • • 9d ago

Next Capital launches Dataspace on five former Fujitsu data centres with 14.5MW

2 Upvotes

Sydney private equity firm Next Capital has launched Dataspace, a national data centre operator built on the five Australian sites it agreed to buy from Fujitsu in July. Gavin Milton-White, previously head of transformation service delivery at Fujitsu Asia Pacific, is chief executive.

Full story: https://certifiedstrategic.com/insights/dataspace-launch-next-capital-fujitsu-data-centres

The five sites are Greystanes and Homebush in Sydney, Noble Park in Melbourne, Malaga in Perth and Eight Mile Plains in Brisbane. Together they hold 14.5MW of IT capacity, according to Dataspace's site specifications, and all five are Tier III designs.

Greystanes in Western Sydney carries almost half of that, 7.0MW on a 35MVA electricity supply. Before the sale, Fujitsu marketed the site for an ultimate capacity of 92MW. The other four sites range from 1.0MW to 2.8MW.

Dataspace plans to grow on those existing sites. It says selected sites in Sydney and Melbourne have development potential, and that space inside the current facilities can be converted as demand grows. Milton-White said Dataspace is designing its future capacity for the higher rack densities used in AI, while keeping its government, financial services and enterprise customers.

Three of Dataspace's five executives come from Next Capital's last data centre investment, Brisbane operator iseek. They include chief financial officer Raj Sharan and chief development officer Ian Porter. Next Capital invested in iseek in 2018 and sold its stake in 2021, when Amber Infrastructure took majority ownership. Next Capital partner James Murphy said the firm sees a significant opportunity to back Dataspace with further investment.


r/AustralianDataCentres • • 9d ago

Sharon AI misses revenue forecasts as its long-term GPU contract prices climb above US$19m a megawatt

6 Upvotes

That revenue miss came in the September quarter, with US$9.9 million reported in results released on 16 November 2026. Analysts polled by Benzinga Pro had expected about US$26.9 million, and the shares fell about 8 per cent in after-hours trading. The net loss widened to US$43.8 million from US$1.6 million a year earlier.

Full story: https://certifiedstrategic.com/insights/sharon-ai-q3-2026-results-revenue-miss-19m-per-mw

That result came with most of Sharon AI's new GPUs still in testing. About 12,000 NVIDIA GPUs for a global technology customer and Indian cloud company ESDS are installed, powered and in final testing. Chief executive James Manning said he expects the technology customer to accept its next tranche in December, with billing from January.

January is also when Sharon AI expects its annual revenue rate to rise from about US$50 million to US$400 million to US$450 million, once about 30MW of its contracted capacity is billing.

The company's newer contracts are also priced higher than earlier in the year. Its long-term contracts average about five years, and Manning said their annual revenue per megawatt moved from about US$15 million to more than US$19 million over 2026. The two contracts signed since the quarter ended were priced at US$19 million and US$18 million a megawatt. The contract book rose to about US$9.6 billion from US$8.8 billion in August, after Sharon AI terminated one customer following a review of its credit risk. Manning said that capacity was reallocated at a higher price.

Sharon AI's Australian GPUs run at NEXTDC's M3 in Melbourne, and the company has a 15MW, 10-year agreement with GreenSquareDC at SYD1 in Sydney. It expects 212MW of capacity across Australia and New Zealand in 2027.


r/AustralianDataCentres • • 10d ago

TasWater says Tasmania's proposed large data centres would use about 30ML of water a year, 0.04 per cent of its supply

13 Upvotes

Tasmania's parliamentary inquiry into AI data centres has heard that six data centre developers seeking water from TasWater, the state's water utility, are preparing development applications. The Greens made the evidence public on 12 November.

Full story: https://certifiedstrategic.com/insights/tasmania-data-centre-water-taswater-30ml

TasWater gave Certified Strategic its figures in a statement from Matt Derbyshire, its general manager of sustainable infrastructure services. It puts the combined demand of the proposed large data centres at about 30 megalitres a year, subject to supply conditions. That is about 0.04 per cent of the 84,247 megalitres it supplies each year.

Three of the six proposals are in the north-west, two in the north and one in the south of the state. Two cannot connect to TasWater's network for now, because they sit outside the areas it services. On some of the proposed connections, water for cooling may be used only between 1 May and 30 September inclusive, up to 15 megalitres a year, and TasWater may restrict or suspend supply at any time. A data centre connected on those terms could not use TasWater water for cooling from October to April.

Firmus said in its September submission to the inquiry that its Launceston site is modelled to run without cooling water for 97 to 99 per cent of its operating hours.

TasWater checks each large water application by modelling its network and what it can supply, and takes into account "the cumulative impact of all proposals", Derbyshire said. On top of TasWater's checks, the state's final expectations for data centre developers, released on 13 November, ask each project to forecast how much water it will use in a year, on average and at its peak.

Beyond water, Tasmania's proposed data centres could need up to about 1,150MW of power, counting Firmus's three sites at 444MW and six confidential proposals that could draw up to 705MW.


r/AustralianDataCentres • • 10d ago

Should water availability matter more when choosing sites for new data centres?

4 Upvotes

I feel water usage gets overlooked when new data centres are discussed. Everyone talks about power, but cooling can put a fair bit of pressure on local water supplies too. I'd be concerned about building a large facility in an area already facing water shortages without looking at the impact first. Have you seen water availability influence data centre site decisions, or does power still come first?


r/AustralianDataCentres • • 10d ago

Southern Cross Electrical wins the electrical contract for NEXTDC's S4, one of the projects outside NEXTDC's pause

2 Upvotes

ASX-listed Southern Cross Electrical Engineering said on 16 November that its business Heyday has won the electrical design and construct contract for the first stage of NEXTDC's S4 data centre at Horsley Park in western Sydney. Builder Multiplex awarded the package, after Heyday received a letter of authorisation in June to start initial works on site. The work is expected to finish in early 2028.

Full story: https://certifiedstrategic.com/insights/southern-cross-electrical-nextdc-s4-contract-300m-awards

That first stage includes the high-voltage switching building and two of the four planned data hall buildings, each four levels high. Heyday's contract covers the site-wide electrical and communications work across it. It has worked on S4 since 2024, giving Multiplex and NEXTDC cost planning and technical advice.

Work at S4 continues while NEXTDC keeps projects without customer contracts on hold. It paused them on 21 October, when a delay to grid power at its M3 campus in Melbourne cut its FY27 guidance. S4's first 250MW is signed to customers, so it sits outside the pause. In the same investor update, chief executive Craig Scroggie said the S4 250MW delivery program was on track.

That S4 contract was one of five awards worth more than A$300 million in total that Southern Cross Electrical announced. Managing director Graeme Dunn called it the largest single announcement of works in the group's history. Force Fire, a Southern Cross Electrical fire protection business, won fire systems work at a second data centre for builder Shape, and Heyday won work on three Canberra building projects. Dunn said the new data centre awards came from "clients for whom we have done significant works previously".

Southern Cross Electrical's FY26 result put its data centre revenue at A$120 million, and at its annual general meeting on 27 October it put the FY27 figure at about A$400 million. Southern Cross Electrical is one of the ASX-listed contractors earning from the data centre build, alongside SKS Technologies and NRW Holdings' Fredon.

NEXTDC has promised the outcome of its capital spending review by its annual general meeting on 20 November. Southern Cross Electrical's half-year result, expected in February 2027, will show how much of the forecast A$400 million in data centre revenue has been earned.


r/AustralianDataCentres • • 10d ago

NEXTDC builder Kapitol expects record data centre starts, and other builders' data centre books are growing too

2 Upvotes

Melbourne builder Kapitol, which builds data centres for NEXTDC and Microsoft, expects the 12 months from November 2026 to be its best year yet for new data centre starts, joint chief executive Andrew Deveson told the Australian Financial Review on 15 November.

Full story: https://certifiedstrategic.com/insights/kapitol-data-centre-builders-best-year-starts

Kapitol is private and reported that its revenue more than doubled to A$1.6 billion in the year to June 2026, driven by large data centre contracts. Net profit after tax rose to A$56.8 million from A$25.5 million, and data centres made up 60 per cent of revenue. Construction data company Hubexo ranked Kapitol first in its 2026 Construction League, with 17 projects worth A$3.503 billion started in 2025.

Fellow Melbourne builder Hickory also more than doubled its revenue, to A$1.34 billion in the year to June 2026, according to figures published by the AFR. Data centres make up 40 per cent of its order book. In Sydney, listed builder FDC reports its signed work by sector, and its signed data centre work rose from about A$225 million on 30 June to about A$465 million on 31 October 2026.

In Oxford Economics data published by the AFR, Kapitol and Hickory are two of the five largest builders of data centres in Australia, alongside Multiplex, Lendlease and A W Edwards. Each has more than A$2 billion of data centre projects that started since 2020, are under way or are committed. In an October briefing, Oxford Economics forecast data centre construction rising from about A$5.3 billion in FY26 to a peak of about A$14 billion in FY29, in 2023-24 dollars.

Kapitol is also preferred bidder for the expansion of NEXTDC's M3 campus in West Footscray, which is waiting on grid power. NEXTDC is keeping on hold any project without a signed customer until it has solved M3's power problem, chief executive Craig Scroggie told investors on 9 November. Deveson declined to discuss M3 and said the timing of some starts is uncertain.

If the flow of capital into data centres changes, Kapitol wants to be able to do other work, Deveson said. It has opened a Brisbane office, led by Queensland general manager James Grljusich, formerly of Multiplex, and is targeting housing, infrastructure and data centre work in the state.


r/AustralianDataCentres • • 11d ago

Jensen Huang resigns after 33 years running NVIDIA: what it means for Australia's AI builds

19 Upvotes

Jensen Huang has resigned as NVIDIA's president, chief executive and director, the company announced on 12 November, US time. Chief financial officer Colette Kress is running the company in the interim.

Full story - https://certifiedstrategic.com/insights/jensen-huang-resigns-nvidia-australia-neoclouds-kress

His exit followed reports of an affair with Alice Huang, a former Megaspeed executive whom US officials believe is a Chinese intelligence asset. Reuters could not reach her. Beijing calls the spying claim groundless, and Megaspeed denies wrongdoing.

Unlike Mark Zuckerberg, Google’s founders or Elon Musk, Huang had no extra-vote shares to protect his position. NVIDIA adopted one vote per share when it listed in 1999, so he held 3.6 per cent of the votes, the same as his share of the company. Mark Zuckerberg, by contrast, holds 61 per cent of Meta's votes on 13 per cent of its shares. Larry Page and Sergey Brin hold 53 per cent of Alphabet's votes on at least 9 per cent of its shares. Elon Musk holds 84 per cent of SpaceX's votes on 48 per cent of its shares. That left Huang's future with NVIDIA's board, where a simple majority was enough to remove him.

The board opened an independent investigation and said it had "no reason to believe that either national security or NVIDIA secrets were compromised". Three days later it accepted his resignation. The board told CNBC on 13 November it had "not formally engaged any potential candidates" to succeed him, and the Financial Times says it has approached Arm chief executive Rene Haas.

Whoever takes the job inherits Huang's chip roadmap. Vera Rubin is ramping into full production, and Rubin Ultra and Feynman are designed for 2027 and 2028. SemiAnalysis reported in July that the Kyber rack had slipped to 2028.

For Australia's AI builds, NVIDIA's money is less certain than its chips. The company holds shares in Firmus. It takes a share of Sharon AI's cloud revenue on 72MW, and it holds a warrant over up to US$2.1 billion of IREN shares. Those decisions now pass to Kress, who The Information says has at times pushed back on Huang's deals. The first is a reported NVIDIA investment in Firmus's private round. NVIDIA reports its third-quarter results on 18 November, Australian time, Kress's first as interim chief executive.


r/AustralianDataCentres • • 11d ago

Tasmania will require large data centres to pay host communities at least A$3,000 per MW each year

5 Upvotes

Tasmania will require large data centres to pay their host communities at least A$3,000 a year for each megawatt of power they contract, under final expectations Premier Jeremy Rockliff released on 13 November.

Full Article - https://certifiedstrategic.com/insights/tasmania-data-centre-community-benefit-fund-3000-mw

Each developer of a facility above 20MW will run its own community fund. Payments start once it operates, rise with inflation, last the life of the facility and stay with the site if it is sold. They sit on top of rates, taxes and connection costs, and the terms go into an agreement each developer signs with the state, which can enforce them. Ellis, the Innovation, Science and Digital Economy Minister, said developers who do not follow it won't be able to proceed.

At the minimum rate, a 100MW data centre pays A$300,000 a year. Firmus buys up to 104MW for its St Leonards site in Launceston, which the ABC said means A$312,000 a year. Firmus told the state's AI data centre inquiry it expects to contract about 444MW across three sites. At the minimum rate, that would mean about A$1.33 million a year.

Beyond Firmus, six further unnamed proposals, listed in a document tabled in parliament on 8 September, need between 505MW and 705MW. Together, the state's proposed data centres would pay about A$2.8 million to A$3.4 million a year if all are built and contracted.

That rate is almost three times the A$1,050 a megawatt that wind farms pay host communities in New South Wales. Canberra asks developers to share benefits but sets no rate, and plans to legislate mandatory standards in early 2027. Rockliff said Tasmania's expectations would be reviewed after six months.


r/AustralianDataCentres • • 12d ago

AirTrunk signs MoU for 1.8GW of data centre campuses in Andhra Pradesh, next to Google's Visakhapatnam AI hub

6 Upvotes

AirTrunk signed a memorandum of understanding with Andhra Pradesh Chief Minister N. Chandrababu Naidu on 13 November for two proposed data centre campuses in Anakapalli district, next to the port city of Visakhapatnam.

Full Article: https://certifiedstrategic.com/insights/airtrunk-andhra-pradesh-1-8gw-anakapalli-mou

The campuses are 1,400MW at Tootipala and 400MW at Rambilli. Rambilli is also where Google is building one of the three campuses of its US$15 billion Visakhapatnam AI hub, its largest investment in India.

The Sydney-founded operator entered India in April when it bought Lumina CloudInfra and its 600MW pipeline across Mumbai, Chennai and Hyderabad. In June it set out a plan to invest more than US$30 billion in over 5GW of new Indian capacity by 2030, and the Maharashtra Government signed a letter of intent for land for a 3GW hub at Raigad, outside Mumbai.

Raigad and the two Anakapalli campuses come to 4.8GW, all under preliminary agreements with state governments. An MoU sets out intentions and is not a final investment decision.

The company says the Anakapalli campuses could create more than 3,100 direct operational jobs and 4,700 indirect jobs, and it plans to hire and train locally through India's Industrial Training Institutes and polytechnics.

While those Indian campuses take shape, AirTrunk is advancing its A$4.3 billion Mickleham campus in Melbourne's north and its proposed Kurri Kurri campus in the NSW Hunter.