How long should a transitional services agreement (TSA) last when the ERP can’t be separated on time?

We're selling a division (divestiture), and given that this event is not that common I couldn’t find many resources to help with my issues. 40 people and one product line go to the buyer, signing is done and close is in about 6 months. I have the misfortune of handling the separation.

I solved a few things already. Access was organised per business unit in Passwork vaults which made list extraction fast (took about ~1h), as I can see who can reach which system in a few clicks and I was also able to download access logs and keep them in our archive (just in case a future auditor asks for them). I was then able to split the laptops because they were all tagged to a person and a cost centre in Snipe-IT. The product has always lived in its own repos with its own build pipeline and transfers as a unit.

Nothing else comes apart that cleanly:

  • Our SaaS contracts were bought as single licence pools. 4 vendors have told me they won't split mid-term, and 2 of those have change-of-control clauses that let them reprice the moment we notify them.
  • The ERP holds 7 years of orders for both halves in the same tables. Splitting it means deciding who owns records that touch both sides, and our finance lead says a fair number of them belong to both.
  • Our file server has folders that were shared across both halves for a decade because nobody expected this.

The buyer wants a 6-month TSA. My estimate is 9 months for the ERP alone, and I don't have the headcount to run IT for 2 companies in the meantime.

How hard do I push on the TSA length before we're committed? And what to do about the data that can't be divided cleanly at any length?

11 Upvotes

14 comments sorted by

6

u/Chris_PDX 19d ago

I do ERP migrations including divestments and other M&A activities.

Any TSA we deal with is finite, typically that covers the expected length of the ERP migration. The migration of data can entail extracting everything that follows the divesture into a DW or lake for posterity, since not everything will make it into the new ERP.

I literally had the conversation yesterday with a client who wanted an ERP migration done by 12/31 so they didn't have to spend another $60k on a yearly license with the vendor. I explained, any cost savings by rushing it will be eaten up the post conversion issues, system stability, and other risks that would come up by virtue of rushing it.

2

u/Lazy_Side_6830 19d ago

Good advice on each, thank you. I'll start doing estimates for each system and write it down with a thorough explanation so they get off my back, I'll even try to get vendor confirmation if needed. I really want this to be done once and only once and if we rush a 9-month job in 6 it'll be ugly. As per the data warehouse/lake, who ends up holding the archive? The records touching both sides are what we’re stuck on, and freezing them doesn’t really answer much (oh and, side note, wanting a migration done by 12/31 is bonkers haha)

4

u/Check123ok 19d ago

Hard to explain to client the cost of bad ERP. It shouldn’t be but somehow it always is

1

u/Chris_PDX 16d ago

My analogy is:

You're asking me to take your 1920's bungalow and disassemble it, move it across town, and re-build it to look like a modern contemporary house.

But I can only use the materials we started with. And the new house has to meet modern code.

That's what an ERP data migration entails.

7

u/phoenix823 19d ago • Bravo

Why is any of this your problem? These are all issues for the buyer to deal with. The term of the TSA is based on how long they want to keep paying your company for services. You don't know how long that is.

  • Your buyer is responsible for new SaaS agreements for the organization they purchased. Your SaaS agreements do not change until it's time to renegotiate. Not your problem.
  • Your buyer is responsible for implementing ERP for the product they bought. You provide them with ERP services for the length of the TSA. Charge them one rate for the first 6 months, give an option to extend 6 more months for 50% more per month.
  • Ownership of finance data is a finance and legal problem. They figure it out and tell your buyer what they can and cannot have. They then import that into your ERP. Not your problem - you're not qualified to opine on this. You're not a lawyer, you're not in finance.
  • As for the file server, what did the buyer agree to? If file transfer is not in the TSA, then nothing gets transferred.

I don't have the headcount to run IT for 2 companies in the meantime.

You only work for one company.

2

u/voumbibist79 6d ago

Yeah that extension penalty is the only thing that actually forces buyers to finish their ERP setup on time

1

u/Check123ok 19d ago

“Ownership of finance data is a finance and legal problem” just want to emphasize this for OP

5

u/cleveraccount3802 19d ago

Two things:

  1. A lot of this is the buyer's problem, they need to figure out how to run the newly acquired business.
  2. You should be asking for significant payment from the buyer for continuing to run this systems as part of the TSA. Ask for more than you think you need and use that funds to hire contractors or whatever you need to do to operate the TSA scope.

2

u/bearcatjoe 19d ago

TSA typically defines extension options usually including payment ramps.

2

u/Check123ok 19d ago edited 19d ago

Hard to say for your situation, I feel like they always play different. I been part of larger situations like yours where Pharma company did carve out for their medtech division and also for soda manufacturers.
I only led the tech side.

What I can say in general is they are sensitive about timing.
I would add more resources instead of proposing more time. Resource constraints is the common denominator.

Assuming your nine-month ERP estimate means nine months after closing?
Maybe do the 6 month with 3 month extraction for ERP only. That might fly better. Service specific and explain why.
You should be able to separate access in ERP for just historical records review vs operations. Give the newco just access to records for finance. That’s what I have done but that’s a small sample

Oh edit let finance/legal define in writing what records are entitled at the beginning not when you are pending changes

1

u/a1anw-cto CTO 19d ago

This is a tough spot to be in. If the ERP split is going to take nine months but the buyer only wants six, you have a significant gap in your operational plan. I would push for at least 12 months if possible. It is better to have the extra runway and terminate the TSA early than to be caught mid-separation without the headcount or systems to support both entities.

Regarding the data that cannot be divided cleanly, look into creating a "read only" instance or a data warehouse layer for the historical records that touch both sides. This allows both companies to maintain compliance and reporting without needing a full logical split of the production database immediately. For SaaS contracts, check if you can negotiate a temporary "bridge" agreement with those vendors rather than an outright split.

1

u/ResilientTechAdvisor 19d ago

I had a client who was afraid of blowing up the deal. Requests for staffing funds, more time, or data restrictions could sound like friction - maybe perceived as surprise charges, weak planning, or withholding purchased assets.

My advice was to start with the buyer’s six-month priorities, then propose a phased transition showing costs, dependencies, and extension options.

For shared records, I recommended the client first agree with the buyer on what each business needed to keep and access. Then the client had legal and finance turn that understanding into an agreement covering custody, permitted copies, security, retention, and costs, with historical access continuing after the TSA ended.

1

u/BearyTechie 19d ago

Didn't you mention any risks while providing your estimates?