Insurance work

Hey yall, my buddy and electrical contractor just recently had a bunch of water damage in his house. Insurance is involved, and the initial check to get things put back together is in the mail.

He’d like me to do the work, and I’d love to have a job I can walk to for a month or so. But, I’ve never done any insurance work as far as submitting estimates to the insurance company and haggling. Generally on those jobs I’m a sub and the money is already there

Any advice for structuring my proposals and making sure I don’t get screwed by their negotiating team?

0 Upvotes

8 comments sorted by

5

u/TheseMFisTrippin 3d ago

DO NOT NEGOTIATE. Have a very detailed scope of work and let the price be justified with details.

Hold firm, the adjuster is slick and their job is to deny/reduce cost.

2

u/berg_schaffli 3d ago

Ok, so generally I just list things out on my estimates with a final sum at the bottom. I don’t share pricing per piece/trade/stage. Should I expect them to want a breakdown of my pricing?

2

u/TheseMFisTrippin 3d ago edited 3d ago

Yes, you need defensible pricing. Line item/qty every little detail, even if you are making up categories. Dust protection, HEPA filtration, new home air filter, blow off driveway after magnetic nail removal, administration/paperwork, fuel/mileage, generator usage, demo/disposal, etc. Look up the Construction Master Format.

2

u/Build68 2d ago

Insurance is its own thing and they don’t care about our desire to estimate in a lump sum. Every line item you can generate that the adjuster can relate to a price list helps you. Insurance contractors have enormous overhead and the price list takes that into account. The money can be good.

6

u/DanTheClaculatorMan 2d ago

Ask your buddy for the adjuster's estimate first. It's usually written in Xactimate, and pricing against their line items makes the back and forth way easier than a lump sum. Expect the first check to be short too - a lot of policies hold back depreciation until the work's done, and if there's a mortgage the bank may need to sign the check. So set your payment schedule around when the money actually shows up, and write up anything you find behind the walls as a supplement right away.

3

u/FunsnapMedoteeee 2d ago

Contact Doug at Assistimate.com Get yourself a proper xactimate estimate. Then you’ll have an xactimate estimate and be seen as professional in the eyes of the adjuster.

2

u/Build68 2d ago

Insurance estimates by resto contractors are usually generated in a program called Xactimate. They are tied to a dimensioned sketch of the damaged area and they take the form of room by room, trade by trade. A typical water damage estimate might be BEDROOM 1: demolition (content manipulation, floor removal, countertop removal, cabinet uninstall with face frames saved for re-use, flood cut, dry out) repair(plumbing and electrical, drywall, tape & texture, paint, cabinet re-build and re-install, countertops, flooring). If you break it down room by room and trade by trade, you will be showing the adjuster something they can relate to their own estimate. This will help them support your numbers to the carrier and get you off of their desk.