r/Grid_Ops • • 17d ago

Grid permitting process

Developers: which step in obtaining grid connections takes longest - is it waiting or actual work? And if it's waiting - is the bottleneck the DSO / TSO? What do they need to do? (Please add your country of ref. in the answer!)

Seems like an unnecessary inefficiency so I must be missing something

0 Upvotes

7 comments sorted by

6

u/Content_Pepper_8575 17d ago

Respectfully, this is pretty well documented in publicly available reports from industry groups (ESIG, etc) and government agencies (DOE, etc)

Also this sub is mostly occupied by control room operators, not grid planners. So while some folks may have input, your core audience here is not usually involved with project development

1

u/IcyState5361 17d ago

Thanks, will check the reports!

1

u/Next_Chicken9739 17d ago

(Canada) Large loads like multiple DFO connections as the project can be delivered much faster without the regulatory hurdles and stakeholder engagement. This is assuming sufficient capacity exist and the upgrade is just on the distribution feeder level.

Anything on the TFO side will require long lead equipment, stakeholder engagement and regulatory process. Looking at multiple years depending on jurisdiction best case.

1

u/IcyState5361 17d ago

Interesting, thanks!

1

u/failureat111N31st 17d ago

Are you trying to ask developers if the grid side is an unnecessary inefficiency? That feels a bit like asking drivers if traffic lights are an unnecessary inefficiency.

1

u/One_Adeptness3803 17d ago

Multiple pieces to this puzzle. One is CEQA, cluster studies that determine impacts don’t occur immediately and usually take a few months to complete, and a big hold up people don’t talk about is the developers drag their heels while evaluating financial benefit of the project and obtaining financing. It does feel needlessly slow but there’s a lot of slow moving parts in the process.

Edit - CEQA is just a California thing but other states have similar processes.

1

u/CressiDuh1152 17d ago

The Operator is nowhere near a significant portion of the holdup.

Regulatory, planning, permitting, and often component lead times are the main hurdles.