Multiple Instance/Monitor Support
Any vibe coders figure out how do this yet? I don't want your vibecoded MS Project alternatives, but I will pay for functional multi instance/multi-monitor support.
r/MSProject • u/Mr_Fogel_1 • 3d ago
Pricing a project and controlling its budget are two different jobs. Why does the budget always change between tender and execution?
I started my career as an estimator and moved into project controls. It took me a while to understand they're two completely different worlds.
Pricing is the basics: you price from the drawings, calculate quantities, collect quotes, and estimate the duration and the team. It's a snapshot, built on what you know at tender stage.
Control starts the moment that snapshot meets reality. Between the tender and the start of execution, almost everything moves: drawings get revised, prices change, scope gets "clarified".
What helps me:
- Before every work package, a quick cost check on site against the current drawings, not the tender ones.
- A monthly checkpoint for budget and schedule together. Monitoring is constant, but the monthly review is where decisions get made.
- A clear contingency rule: one general pool or one per activity, and above all, who approves using it.
The tender budget isn't wrong. It's just the first version.
How big is the gap between tender and execution on your projects, and where does it usually come from?
r/MSProject • u/Suhail-Sayed • 5d ago
Project going away.
Did yall see the announcement that Microsoft is not interested in Planner Premium (Dataverse Project for the web) anymore and they will simply add some new features to Planner Basic and put that behind a license!
No more Project Management tooling in Microsoft except for D365 Project Operations!
r/MSProject • u/Purple-Rain-1430 • 6d ago
Does anyone actually use work contours or is everyone just leaving assignments on flat?
I’ve been using MS Project for years and only recently started taking contours seriously, so I’m curious how common it is.
By default every assignment is flat, so if someone’s on a task for four weeks at 50%, Project assumes they’re putting in the same effort every single day. That’s almost never how work actually goes. Design work ramps up slowly. Testing tends to peak toward the end. A lot of tasks start light while people finish other things, then spike.
Project already has the options for this, front loaded, back loaded, early peak, late peak, bell, turtle, double peak. But in most schedules I’ve seen, nobody touches them. Everything stays flat, and the resource usage view ends up showing a nice even spread that doesn’t match reality.
Where it bit me was resource levelling across a few projects. The flat assumption made someone look fine in week three when in reality they were slammed that week and fairly quiet in week five.
The catch I’ve found is that contours can mess with duration depending on the task type, and they make the schedule harder to explain to people who don’t live in Project. Which might be why most people skip them.
So do you use contours? If yes, which ones and for what kind of work?
r/MSProject • u/ZC_ROK • 6d ago
P6 LOE Activities — How Do You Handle Duration, Progress, and Calendars in Practice?
Hi everyone,
I've been working in Planning and Project Controls for over 20 years, mainly on Oil & Gas and Offshore EPC projects.
I'm curious how other P6 planners handle Level of Effort (LOE) activities in real project schedules, especially when the schedule is updated regularly.
A few practical questions:
1. LOE relationships and duration
- Do you normally tie LOE activities to discrete activities using SS and FF relationships?
- Have you experienced unexpected LOE duration or date changes after rescheduling?
- How do you handle LOE activities spanning multiple calendars?
2. LOE progress
- Do you generally rely on P6's Duration % Complete, or do you use a separate progress measurement method?
- How do you deal with LOE activities that extend because their underlying activities are delayed?
3. LOE and earned value
- Do you assign budgeted manhours or costs to LOE activities?
- If so, how do you measure earned value without overstating actual project progress?
4. Schedule validation
- What LOE-related issues do you most frequently encounter when reviewing contractor schedules?
- Do you apply any specific checks to prevent LOE activities from misleading schedule performance reporting?
I'm particularly interested in differences between contractor-side and client/operator-side practices.
No confidential project information needed — just practical experience and lessons learned.
Thanks in advance!
r/MSProject • u/platypus_farmer42 • 8d ago
Is there a way to create alternate start and finish dates on one task (and therefore all subsequent tasks) based on different durations?
For example, I have a task and the team genuinely does not know if it’s going to take 1 day or 30. I want to view the possibility of both at the same time, and what effect it has on all downstream tasks. I know there are multiple different duration columns as well as start and finish dates, but these must be manually entered and they do not create a “second” path of downstream tasks. I’m thinking the only way to do this is to baseline the schedule once as one possibility and then just leave the schedule as the other, but I’d like to know if there’s another way. Another way to think about it would be to have a “best case” critical path vs “worst case” critical path. Thanks.
r/MSProject • u/Ill-Cryptographer344 • 11d ago
I built an .mpp comparison that pairs tasks by Unique ID only - could someone check it against Compare Projects?
Where it started: someone on the Microsoft forum generated .mpp files from VBA, and Compare Projects showed every task as removed and re-added, even though names, dates and Unique IDs matched. My guess is that for files that weren't saved from each other Project looks at more than the Unique ID, maybe the task GUID it has had since 2010, but I haven't confirmed that. If someone knows, I'd like to hear it.
My comparison uses only the Unique ID. The ID column can't be the key, because inserting one task renumbers every row below it, while the Unique ID stays with a task through inserts, moves and renames. The report still shows each task's ID, so you can find it in your own copy.
Per task it checks the name, the parent (so a task moved under another summary shows up), duration, % complete, the milestone flag, start and finish, and whether the task is critical. For links it checks type and lag. Summary tasks that moved are listed separately, so a phase that slipped because of one task doesn't bury the task that caused it.
A few things to know:
- Durations in different units are converted with Project's defaults: 8 hours a day, 40 a week, 20 days a month. If your file uses 7.5-hour days, 1d and 7.5h will show up as a change.
- Date shifts are counted in calendar days, not working days.
- Critical is read from the file as Project saved it. Nothing gets rescheduled.
- It doesn't compare work, cost, resource assignments, constraints, baselines or notes yet.
- If the two files share fewer than a third of their tasks by Unique ID and name, it warns that they probably aren't versions of the same plan.
The files are read on the server with MPXJ, kept in memory and not stored. It reads .xer too, but I've tested that less.
What I'd like from anyone with a pair of versions: does it disagree with Compare Projects anywhere, and is there something you check every week that it misses?
r/MSProject • u/Spiritual_Nobody3833 • 13d ago
AI plugin for MS Project that builds schedules from drawings. What a fantastic tool.
reddit.comr/MSProject • u/Artistic_Zone2444 • 14d ago
AI plugin for MS Project that builds schedules from drawings.
I built an AI add-in that drafts construction schedules inside MS Project from drawings and specs. Looking for honest feedback
Hi all, I’m Jonas, co-founder of Karmen (full disclosure: this is my product).
We’ve built an MS Project add-in that reads construction drawings and specs and drafts a logic-linked schedule right inside Project. You can then edit activities, logic and durations alongside it.
Here’s a short demo: https://youtu.be/2rUlPgdYrm8
I’d love feedback from people who use Project every day.
r/MSProject • u/Vasivid • 17d ago
Sandbox / what-if mode in project planning and scheduling
reddit.comr/MSProject • u/Mr_Fogel_1 • 19d ago
Free 1-hour call on construction scheduling, cost control & AI – send one MS Project file ahead and I'll bring findings (remote, Israel)
Hi all,
I'm Kobi, a senior PMO / project-controls person who has worked on large infrastructure and construction projects since 2012 (MBA in Finance). I'm taking on a few remote, part-time clients and would rather start with a useful conversation than a sales pitch.
\*\*The offer:\*\* a free one-hour call on any of these:
\- Scheduling in MS Project (logic, critical path, updates, look-aheads)
\- Budget and cost control, forecasts, earned value (EVM)
\- Process improvement – especially automating recurring project-controls reporting with advanced Excel models
\- Practical AI in construction – how I actually use tools like Claude Code and Gemini day to day
\*\*Optional:\*\* send me one MS Project schedule in advance (any free sample review is up to 50 activities). I'll go through it and come to the call with concrete findings.
\*\*Time zone:\*\* I'm in Israel (UTC+2) – about 2 hours ahead of the UK and 7–10 hours ahead of the US. Send a file at the end of your day and the review is done by your morning; UK folks get a good overlap with their workday.
No obligation. DM me if that's useful.
r/MSProject • u/randhir_manekar • 21d ago
Built fast, switched on late: how do you carry utility connections and other off-programme dependencies?
Three stories from the last three weeks: a £2bn data centre in Essex told it won’t get grid power until the 2030s, a Melbourne data centre operator halting its shares over a delayed power connection, and Saudi giga-project awards running at roughly a third of 2023’s.
What struck me is that none of them is a construction failure. The buildings got built. The dependency that killed the date (power, approvals, a shifting owner priority) was never on the programme as something anyone owned.
Disclosure: I run DeliverIQ, a series of live sessions for project controls and delivery people. Season one is 14 sessions from January, with practitioners covering things like which programme to submit when you’re late, aligning stakeholders before payments start, and turning cost reports into decisions. I’m not posting a link here; happy to answer questions in the comments.
Curious how others handle off-programme dependencies like utility connections. Do you carry them as milestones with an owner, or as risks?
Here are the sessions to register: https://deliveriq.live/sessions
Contact for any info: info@deliveriq.live
r/MSProject • u/WaveLoose4228 • 23d ago
Creating dashboard
Hi,
I just began a new mission in a rather big project that has been running for 2 years and ain't doing well. (Basically they had to undo the engineering phase to redo it almost entirely). I'm not the new project manager but the right hand as they like to call : the time master. (Yeah I know, cool title 👀) They told me to use Msproject. As I didn't touch this software for decades, I started to devour all the tutos on the internet to catch up and ended up with 2000-ish lines planning. I'm currently looking up the base guide/baseline (which I still don't have a complete grasp on it, but it's a matter of time) to set up variations to track the reality of the project. However, big boss asks me to make a presentation/dashboard each week for the next 2 weeks. Is there any way to do it the smart way ? Or am I doomed to just manually gather what I need to put in the slide ?
r/MSProject • u/Mr_Fogel_1 • 26d ago
How detailed should a baseline schedule be for a $50M+ project?
Activity count, maximum durations, or something else?
I've seen baselines for similar-size projects range from 150 activities to over 3,000. The thin ones can't show who's late or why. The huge ones can't be updated honestly every month, so the progress turns into guesswork and the logic quietly decays.
The rules of thumb I work with: no activity longer than about one update period (20-25 working days) unless it's procurement or a long lead item, every activity has a single responsible party, and the level of detail matches what the site can actually report on each month.
What do your specs or your own experience call for? Do owners on your projects set a minimum level of detail, or is it left to the contractor's scheduler?
r/MSProject • u/Mr_Fogel_1 • 26d ago
How detailed should a baseline schedule be for a $50M+ project?
reddit.comr/MSProject • u/Rude-Scarcity-1138 • 27d ago
Big curved screen
Hey,
On my work I got a 1m flatscreen curved. I thought that would be great for MS projects and it could if I want to work in more projects at ones. But if i do View all it splits them not like I want them. I want 4 in a row not in a square.

Is there anny way i can change this not by hand? but that it splits 4 or 3 in a row?
clicking view again does not work.
Thanks!
r/MSProject • u/Taurian23 • 29d ago
Version compatibility
Hey, just a short question;
Is it possible to edit 2016 .mpp files with Project 2024, so that they can stil be opened and edited with Project 2016?
r/MSProject • u/Mr_Fogel_1 • 29d ago
Do you let MS Project auto-calc percent complete, or do you enter physical % complete and drive EV from that?
Been scheduling construction projects since 2012 ($30M-$150M range), and one setting I've seen quietly wreck earned value reporting is mixing duration % complete with physical % complete. The Gantt looks fine, but SPI ends up measuring time elapsed instead of work actually installed.
My habit now: physical % complete for EV, set at task level, with the earned value method chosen deliberately per project. Curious how others here configure it - and whether anyone actually trusts the built-in EV fields or exports everything to Excel anyway?
r/MSProject • u/Numerous-Wonder6376 • Oct 25 '26
Integrated Master Scheduler
reddit.comSharing across communities that have IMS personnel seeking a new opportunity.
r/MSProject • u/smilu_var • Oct 24 '26
I'm a PM-turned-builder. I made a basic planner with MS Project-style scheduling that the whole team can use, not just the PM. Would love feedback from working PMs.
reddit.comr/MSProject • u/Little_Classic6023 • Oct 21 '26
For those who moved off MS Project, where did you end up and would you pick it again?
With Project Online now retired, our team is finally having the conversation we’ve been putting off for years: where do we actually go next?
Some context. We’ve been on MS Project for a long time, mostly for scheduling. Dependencies, critical path, baselines, resource assignments across a handful of concurrent projects. It does the scheduling part really well. What it’s never done well for us is everything around it. Getting the wider team to actually use it, collaborating in real time, and keeping it current without one person being the Project person who maintains the file.
Microsoft’s suggested path is Planner premium, Project Server Subscription Edition, or Dynamics 365 Project Operations. I’ve looked at all three and I’m not convinced any of them is a clean fit. Planner feels lighter than what we need on the scheduling side, Server means self-hosting again, and Dynamics feels like a much bigger commitment than our size justifies.
So I’d really like to hear from people who’ve already made the move: where did you go and what was the main reason you picked it? How painful was the migration? Did you manage to bring existing .mpp files over or did you rebuild from scratch?
Especially interested in anyone running multiple projects with shared people, since that’s where we feel the most pain.
r/MSProject • u/Brilliant-Focus-4140 • Oct 18 '26
I built a free tool for comparing Microsoft Project files — looking for feedback
ganttscan.comI've been working on a tool called GanttScan that makes it easier to compare and analyse two Microsoft Project (.mpp) schedules.
The idea came from wanting a quicker, clearer way to understand the differences between programmes without manually digging through activities and dates.
It can be useful for comparing baselines against current programmes, assessing delay impacts, reviewing mitigation scenarios, comparing alternative schedules, or simply understanding what's changed between versions.
Currently, GanttScan lets you:
- Upload and compare two MPP files directly in your browser.
- Identify changes to activities, dates, durations and logic.
- Review critical path differences.
- Explore the findings through interactive dashboards.
- Export the comparison as a PDF report.
It's completely free, with no account or installation required.
I'm still developing it and would genuinely appreciate feedback from anyone working with Microsoft Project, whether you're a scheduler, project manager, engineer or someone who regularly reviews programmes.
Particularly interested in hearing what you find useful, what's missing, and what would make it more valuable in your day-to-day work.
r/MSProject • u/Sheeebooo • Oct 17 '26
I looked at ~300 real .mpp schedules: 86% had no baseline saved, 63% had tasks with no links
Disclosure up front: I build Onplana, and these numbers come from schedules people uploaded to our free tools (a schedule health check, an .mpp viewer and a desktop app). No account was needed, we only kept counts, and nothing from fewer than 20 schedules is reported.
What the data shows:
- 6% of 230 plans finish on or before their planned date in at least half the simulation runs (P50). At P80 it is about 6% too.
- The typical slip is 12 days at P50, 18 days at P80, about 5% and 8% of the plan's length.
- 86% of about 310 uploads have no baseline saved.
- 63% have tasks with no predecessors or successors; 48% have a milestone nothing feeds into; 44% already break one of their own date constraints.
- Median plan size: 103 tasks.
The counterintuitive one: plans with no links at all show a much smaller P80 slip (4 days) than linked plans (22 days). That is the simulation having nothing to propagate, not better planning. An unlinked plan looks more certain than it is.
Caveats, because this sub will rightly ask:
- These are plans people chose to run through a checker, so the sample leans toward plans someone already worried about.
- The simulation uses default duration ranges, not ranges the planner chose for each task.
- Sizes, not industries: we do not collect what the project is.
Full breakdown, method and the raw aggregates (CC BY 4.0) are in the first comment.
What would you want to see split out next: by plan size, by Project vs Primavera, or by which DCMA checks fail?