Neutron Has Archimedes Qualification Even Started Yet?

https://x.com/RocketLab/status/2123141853528871143

This quote seems a little revealing:

"Once final development testing is completed we will down-select our final qualification configuration of hardware and will begin delivering engines every 8 days to the stand for flight ATP testing."

It seems to imply they have not yet chosen the design they want to qualify. Unless they've conducted multiple complete qualification campaigns on competing hardware configurations, that means the actual engine qualification test campaign is still ahead of them & the qualification engine may have not even been built yet!

47 Upvotes

66 comments sorted by

26

u/mkvenner24 8d ago

They are clearly testing. Configuration isn’t locked. Hence development is ongoing. Assuming TRL 6. 650+ test firings is a really good sign.

3

u/wallybal24 8d ago

Testing never ends in a program like this! What is alarming is that they haven't finalized their flight 1 config. There's a whole lot of work between engine qualification and launch.

4

u/Historical_Air_8997 8d ago

Like you said testing never ends, they’re always looking for ways to make small improvements.

So, why finalize flight 1 config before they’re close to flight 1? As long as they’re confident they could put forward an engine that’d qualify, they may as well use the time the rest of the rocket needs to improve their engines.

2

u/bildasteve 8d ago

Yep correct - we know they are in full production of the Archimedes engines from a recent video - we also know that the testing they are doing now is just tweaking fuel mixtures, different nozzles and running them through off normal event testing. I don’t think any structural changes are being made. But I’m sure we will find out soon enough.
🤔

0

u/wallybal24 8d ago

They ARE close to flight 1, or at least that’s what they’re telling us.

1

u/Historical_Air_8997 8d ago

That’s valid, they should be showing some progress soon or I’d start getting a bit worried. But if they can deliver an engine every 8 days they need less than a quarter to make enough for the first flight. I think very earliest for flight 1 is Q2 27, so if they aren’t delivering engines by mid to late Q1 then either the engines and haven’t qualified or some other part isn’t.

This could potentially be used as an early indicator on when flight 1 will be. If we see them pumping out engines and delivering them then that could be a sign final flight testing is less than 90 days out.

1

u/wallybal24 8d ago

It would be a mistake to assume first shipset ATPs will go smoothly

2

u/Sonic_the_hedgehog42 8d ago edited 8d ago

Yes, Archimedes qualification has actively progressing at NASA's Stennis Space Center in Mississippi and the program is approaching its final stages.

2

u/Sweeperthinks 8d ago

Not if you frontload the work inside of engine qual testing. SPB has stated 1000 times they want to learn on the ground not in the air. Look how many rumors started on the BE-4 because of something that may not be related.

1

u/wallybal24 8d ago

Yeah but that isn’t compatible with launching soon. And realistically you need to actually finalize your design like a year before launch

0

u/guggi_ 8d ago

As if there was not even more work with stage 1

11

u/RugbySink 8d ago

At a certain point more test firings without a qualified engine is a bad thing. They originally thought these engines would’ve been qualified and ATP’ed over a year ago, but if they are still dev testing then they haven’t ironed out all of the issues in their engines yet.

7

u/Ok-Bridge-2979 8d ago

They've spoken in previous videos about streamlining and automating a lot of the manufacturing processes. I guess my point is that they could be happy with the current design but still be looking at ways to improve manufacturing efficiency? Rather than necessarily making changes to the engines overall design.

0

u/RugbySink 8d ago

If they were happy with their current design I think the company would want to qualify their engine so they can publicly announce the milestone. You can make small manufacturing improvements after your engine is qualified.

2

u/itgtg313 8d ago

"You can make small manufacturing improvements after your engine is qualified."

that's not how it works mate

1

u/wallybal24 6d ago

depends on the improvement

1

u/Sonic_the_hedgehog42 5d ago

Peter beck plans to test the engine right up until launch day.

https://youtu.be/mmD28kHDC2w?si=LE89D-rlqQlGSJJR

Instead of projecting your emotions, maybe listing more and being less emotional.

1

u/RugbySink 8d ago

I’m not saying they wouldn’t need to re-qualify their design/manufacturing improvements on a block 1.1/1.5/2 engine (whatever they want to call it), I’m saying it doesn’t make sense that they would hold up their qualification campaign on a working engine to improve manufacturing efficiency.

7

u/mkvenner24 8d ago

Not sure that is how it works. I work in rotorcraft and when we make “small manufacturing improvements” on flight critical parts we have to go through FAA testing.

1

u/RugbySink 8d ago

That’s exactly my point, why would they delay qualifying their engines by waiting for improvements in manufacturing efficiency?

5

u/Key-Suggestion4784 8d ago edited 8d ago

If the entire programme is held up elsewhere (tanksy 2.0) then they can use the time to refine the engine and streamline manufacturing before they qualify it, to avoid having to requalify it. I'm not saying this is definitely the case, but it would make sense.

They can run all the qualifying tests so that they know they can tick that off when required, but if they know the whole programme is being delayed by other teams they can use the time to iterate before qualifying, knowing they can do so at relatively short notice if required. They aren't going to qualify the engine and sit around twiddling their thumbs so why not take advantage of the time they have now instead of qualifying then iterating.

2

u/RugbySink 8d ago

Definitely, I hope you’re right.

3

u/mkvenner24 8d ago

So they don’t have to do it between flight 1 and 2. The idea is cadence not launching once and then waiting month to years before launch 2.

New Glenn took 10 months between launch 1 and 2. Electron took 8 months. Falcon 9 took 6 months. Vulcan took 9 months.

Figure out the changes you know you need to make before qualifying and launching. Rocket lab is not known for taking the shortcut

1

u/RugbySink 8d ago

That’s a very generous interpretation. I hope you’re right and they’re using the delays from their structures to improve a flight worthy design.

2

u/Ok-Bridge-2979 8d ago

Interesting, sorry, I didn’t realise they could still make tweaks to the manufacturing processes after qualifying. But yes, I agree with you then.

3

u/RugbySink 8d ago

It depends on what the tweak is, some tweaks might warrant re-qualifying the engine.

My main point is that I don’t understand how they haven’t qualified block 1 yet, and the fact that they haven’t tells me they’re still working through issues.

2

u/yohiyoyo 8d ago

There's not that many significant 'small manufacturing improvements' you can do before you need to run through a qual campaign again.

They're clearly trying to avoid locking in a design until it's very mature

2

u/RugbySink 8d ago

Totally agree, that’s what I mentioned in another comment. I just think they’re struggling with this engine more than their squeezing out manufacturing efficiency.

1

u/ActionPlanetRobot USA 8d ago

exactly

4

u/TKO1515 8d ago

Yeah that’s my read. They will get there but implies had way more issues than they thought

14

u/FilmPhotoMaker 8d ago

https://www.reddit.com/r/RKLB/s/TkYfoBE5H2

Also key words: “will begin delivering engines … for flight ATP”. Implies they didn’t produce flight engines yet.

4

u/Expensive-Ad-2707 8d ago

If they decide configuration. Choosen one tests already been complete. But if they add something new they need to decide. Is it effect working prossess. Is not they dont need to test again. Just serial production tests like rutherford engine.

5

u/wallybal24 8d ago

You're meant to conduct a complete engine qualification campaign on complete & representative hardware.

2

u/Expensive-Ad-2707 8d ago

But also they need to produce at least 8 rocket. 8*8= 64 days

2

u/pund_ 8d ago

10,9 for the first stage and 1 for the second stage as well

4

u/wallybal24 8d ago

well yeah they can't be making flight engines if they don't know the design yet

7

u/FilmPhotoMaker 8d ago

That’s my point, they had multiple official communications that they either started qual or in the process of qualifying the engines starting in 2024. The latest statement means they have been having issues. Otherwise the commentary will be “developing the next iteration of engines” and taking credit for having a flight 1 design.

That’s not been the case, they have been intentionally vague regarding the testing of engines.

4

u/wallybal24 8d ago

preaching to the choir haha

0

u/PlanetaryPickleParty 8d ago

They could build and qualify all flight engines in a little over 2 months. It's not unreasonable that they've held back because of where everything else is in the timeline. Could easily be 2 months before tanksy is ready to ship to Wallops.

2

u/FilmPhotoMaker 8d ago

Tied with my comment about their marketing: https://www.reddit.com/r/RocketLab/s/LsebomZziG

They started qual back in August 2024, more than a year before Tanksy failure. They would not have anticipated schedule impact from the tank failure that didn’t happen yet.

1

u/wfriedma 8d ago

They can produce an engine every 8-10 days. I would worry about that

6

u/methanized 8d ago

I have been a bit of a skeptic of the Archimedes timelines, but I don’t take this to mean qualification isn’t started. I would guess that some component on the engine (e.g, injectors or turbine wheels or a cryo valve or whatever) has multiple potential configurations and they are not sure which one will pass qualification successfully. Flight engines are potentially ~completely built and just awaiting these last components to be swapped/confirmed

It is not uncommon to qualify a whole engine outside of the turbine wheel, for example, and then run a separate campaign to qualify the turbine wheel

9

u/wallybal24 8d ago

For a major component like that you would need to repeat much of the duration & starts of an engine qual campaign to qualify it.

-1

u/methanized 8d ago

Yeah, but you are at least going into that testing with much lower risk/uncertainty since you know the rest of it works

It’s still not great, but my described scenario would essentially be that the engine partially failed qual, rather than that it hasn’t started  

1

u/wallybal24 8d ago

Yeah it's believable they've tried to qualify their engine already

2

u/FilmPhotoMaker 8d ago

Can’t be any more clear than this statement in 2024.

“The Archimedes engine development and qualification campaign continues to progress well”

https://x.com/rocketlab/status/1840143678171689435

14

u/FilmPhotoMaker 8d ago

It seems most people can’t understand this.

RL has been advertising every accomplishment like the second stage tank cryo proof operation as their stage 2 qualification. Sure, it was a structural qualification (arguable since the test didn’t apply external loads…), but they were vague in the description in saying it’s a stage 2 qual. It’s clear that what they tested years ago was just a structural unit without any fluid trays + plumbing, COPVs, avionics, etc as you clearly see them on the flight hardware. They mentioned that qual multiple times in multiple earnings calls. Same for the hungry hippo test as stage 1 qual (it’s not)

No way in hell RL would they not advertise a flight 1 engine qual half a dozen different ways. They would be shouting it from on top of a hill every chance they can.

1

u/user74729582 5d ago

So... Don't buy?

3

u/burmese_python2 Holder of many shares 8d ago

Not even close.

5

u/Daniels30 8d ago

By that statement the answer is no

0

u/Mission_Height8489 8d ago

These guys are designing an engine that would be similar trying to win the 24 hours of Lemans over and over and not simply a 5 second drag strip race. Trust in the leadership, they’ve set difficult qualification goals so that you have confidence to go the full mile land load loach in 24 hour TAT. They want this engine to be like that of a 90’s Honda, no matter what you do it just goes.

5

u/wallybal24 8d ago

40 starts and 3600 seconds of runtime is not some insane overqualification for an engine you want to reuse. You are mistaken about how difficult their qualification goals are.

4

u/FilmPhotoMaker 8d ago

As a point of reference, Relativity Space qualified their engine in August 2025 with 60+ hot fires, their first post about engine qual says it had 11 hot fires in May of that year alone.

https://x.com/relativityspace/status/1958989627278467275

https://x.com/relativityspace/status/1932887412428140863

I could not find Stoke announcing their engine qual, but since they are shipping ATP’d flight engines to Cape and saying development is done, it sounds like they may have qualified their engines already.

https://x.com/stoke_space/status/2123416707687424233

Here is Stoke doing with their staged combustion engine in 2025 what Rocket Lab was saying they were doing with Archimedes just a week ago:

https://x.com/stoke_space/status/1930609298473668992

1

u/FilmPhotoMaker 3d ago

New point of comparison dropped: Zenith qualled two engines to about the same number of starts (45 assuming both engines had the same number of starts) as the Archimedes target. https://www.stokespace.com/news/pathfinder-arrives-at-launch-site

-1

u/Mission_Height8489 8d ago

Agreed, but it’s also not a “let’s cross our finger” and hope it works. It’s a “we picked this because it gives us confidence for the future”. Regardless of the campaign, either you trust SPB and team to deliver on their long term vision and this is just another accumulation opportunity, or you bought in on hype with little knowledge and think we’re a rocket company. It hurts to be down 400k like me from ATH, but I’m still looking at a 400% gain right now. I believe, let’s give them time to execute. They are trailblazing, sometimes you need to slow down and take a detour, but if you’re aligned with the direction then ignore the stock price and look at what the co is doing…..

6

u/1foxyboi 8d ago

Kinda ridiculous how much they are flaunting their volume of tests and the hours of burn, but won’t qualify them.

2

u/nethan365b 7d ago

rocket lab's q3 10-Q (filed 9 nov) doesn't use the word qualification for archimedes. it says engine testing continued through q3. the bigger line is that in october they found voids in a composite tank dome, need a replacement forward dome, and now expect neutron's first launch in 2027, with a more specific timeline after the first-stage tests. the same filing says the stage 1 tank ruptured in a hydrostatic pressure trial on 21 jan 2026.

2

u/Savedacat_saveplanet 8d ago

They have already produced the hardware that will fly in regard to the engines. Peter beck has stated multiple times they will push the engines for as long as they can and qualify them when ready

1

u/B1g_C4p1T4l 7d ago

iirc on the Q3 call Beck said AVac just cleared cold box testing and that moves the qual campaign closer to the finish line, so it's running, just not done. the forward dome voids were the bigger schedule hit imo, a fresh AFP dome means a full NDT round again before it goes back in the stack

1

u/No_Independent337 6d ago

Every 8 days to the stand before they've even down-selected a config? lol. Thats the part everyone glosses over. That movie only ends one way: a slipped launch date

0

u/start3ch 8d ago

You generally design the engine, put it through ATP testing, then put a select few that will never fly through Qualification testing.

3

u/wallybal24 8d ago

Qualification is meant to come before ATPs

0

u/steven2410 8d ago

First flight 2028 that is if we are lucky lol

-1

u/Scared_Step4051 8d ago

the shambles continues, this won't fly till late 2027 at the earliest, more like 2028 imo (if ever successfully)

-1

u/CamusCrankyCamel 8d ago

I don’t know if the post is accurate but if it is and they had to go back into dev for important components even 2028 is looking unlikely