Upcoming In-Street Work
Monday, November 23 - Monday, November 30
In observance of the Thanksgiving holiday, work will not occur on Thursday, November 26th and Friday, November 27th.
Work within the laydown yards at 650 Atlantic Street and 97 Hamilton Avenue will continue during the day, from 7 a.m. to 7 p.m.
Overnight work on Vine Road has been completed.
Moving forward, crews will continue underground duct bank installations and vault interconnection work on Vine Road between Barmore Drive and High Ridge Road
Monday through Wednesday this week from 9 a.m. to 2:15 p.m.
Crews have paused vault interconnection work at the intersection of Vine Road and Pepper Ridge Road. Steel plates will remain on the road while this work is paused.
Crews will begin curb restoration on Vine Road on Monday, November 23rd. Following this restoration, crews are expected to begin roadway restoration on Vine Road.
Schedule updates will be provided when available.
Crews anticipate beginning underground duct bank installations on Strawberry Hill Avenue on Monday, November 30th.
This work will begin at the vault location on Strawberry Hill Avenue near the intersection of Colonial Road and continue north towards Grade A Market (563 Newfield Avenue), working Monday through Friday from 9 a.m. to 4 p.m.
Residents on the route are encouraged to reach out to coordinate driveway access.
Underground duct bank installations on Newfield Avenue between the Vine Road intersection and 884 Newfield Avenue will continue Monday through Wednesday from 9 a.m. to 4 p.m.
Work will travel south down Newfield Avenue, and traffic will operate in a one-way alternating pattern.
Additionally, we will be actively working on the following streets, excavating as part of the underground duct bank installation process:
• Colonial Road between Strawberry Hill Avenue and Pilgrim Walk: Work Hours: Monday through Wednesday between 9 a.m. and 4 p.m. This work is expected to continue through the end of the year.
• Traffic Operations: The intersection of Strawberry Hill Avenue and Colonial Road will remain closed at the discretion of the Stamford Police Department
• Vine Road between Barmore Drive and High Ridge Road
• Work Hours: Monday through Wednesday, between 9 a.m. and 2:15 p.m
*Access will be maintained to all homes and businesses*