r/StructuralEngineering • • 2d ago

Career/Education Managing schedule/workload

Not a complaining post.

I’m in a smaller firm where I have pretty good freedom to manage my schedule and clients. I like to pretend that I have a good handle on my schedule but it’s mostly guesswork and talking to clients before I blow through a deadline. Just wondering if anyone has any good rules of thumb, planning tricks, or software they recommend for forecasting how much time you need between milestones.

10 Upvotes

5 comments sorted by

9

u/BlazersMania 2d ago

I run my own solo small residential firm, no matter my backlog I always tell customers/clients about 2-4 weeks out to return preliminary plans. If I am actually slammed that may extend to 4-5 weeks.

I've learned that if your lead time is longer than a month out for residential then they will probably go look for a different firm. For the most part I can keep to my word about my timelines, if I will exceed them I make sure to let the architect/designer/home owner know before I cross that threshold.

9

u/not_old_redditor 2d ago

I don't know of any easy tool you can use to forecast how long it'll take you to do a project. Just experience. Most people I know will use excel spreadsheets to break down hours for different tasks and add up to a total fee.

8

u/trojan_man16 S.E. 2d ago

It so much depends on your resources and type of projects.

For myself, I just assume everything is going to take me twice as much as I think.

Not because I’m slow, but because there’s always BS you can’t control slowing you down. Managers, contractors and clients on other jobs etc.

I rarely miss deadlines. Maybe an hour or two late at most. I’ve only had to ask for more than a couple of hours a handful of times in my career.

1

u/Prestigious_Copy1104 2d ago

I feel like I do the opposite of this.

2

u/scrollingmediator P.E. 2d ago

Solo residential firm. I keep timelines fairly vague unless they ask very specifically (~50%). The trick is just overestimate. If you're anything like me, I tend to over promise for people that I like, and overestimate for people that are annoying or whose job is a PITA.

I've been working on approaching it differently than "will the client be happy or not". They will be happy in the end if you are quicker than you said. If they're unhappy with your timeline in the beginning, that's actually a win-win because you both dodge a bullet of an incompatible relationship.

I do have a "# days" next to each job on the list, but that's a rough estimate and the minimum number is 1 to account for all the phone calls and construction revisions that come up.

My current lead time per the list is 58 days. Smaller projects I still try to get done in about a month. Bigger projects are still happy if I'm chipping away between small projects.

Underpromise, over deliver and you'll soon create repeat customers that stop asking about time altogether because they know you'll get it done. That's the other 50%.