r/agile • u/ClickOk5811 • 13h ago
Retro action items that never get done: four common weak ones and how I'd rewrite them
Most teams I read about run retrospectives and leave with a list of action items, and then the next retro starts with "we didn't do those." I don't think the cause is usually laziness. I think many action items are written in a form that can't be done or can't be checked.
Here are four examples (constructed, typical of what I see described, not from a specific team), with a rewrite:
| Weak version | Why it's hard to finish | Rewrite |
|---|---|---|
| "Improve communication" | No end state, no owner | "Add a 10-minute sync with the design team every Tuesday; Priya sets it up by Friday." |
| "Write more tests" | Can't tell when it's done | "Add a test for each bug we fix this sprint; reviewers check it in the PR." |
| "Be more careful with deploys" | A feeling, not an action | "Add a 3-item pre-deploy checklist to the release ticket; Marcus drafts it by Wednesday." |
| "We should look into the flaky build" | "Look into" has no result | "Spend up to 2 hours on the flaky build, and post what we found; Lena owns it this sprint." |
What the rewrites have in common:
- One owner (a person, not "the team").
- A visible end state: something you could see or tick off.
- A date or a sprint, so it can't float.
- Small enough to fit in the next sprint, or explicitly bounded ("up to 2 hours").
- It lives in the backlog or the board, next to the other work, not only in a retro document nobody opens.
A couple of practices that seem to help (as far as I understand):
- Limit the retro to one to three actions, so they can actually be done.
- Start the next retro by reviewing last time's actions before generating new ones.
- If an action keeps slipping, either the problem isn't important enough, the action is too big, or something else is blocking it. That's worth discussing instead of re-adding the same line.
Where this can go wrong:
- Over-specifying can turn a retro into a task-assignment meeting and shut down real discussion about what's wrong.
- Some problems (trust, workload, unclear priorities) aren't solved by a ticket, and forcing an action item onto them can feel hollow.
- Naming an owner in the room can put pressure on the most junior or least senior person. How owners get chosen matters.
How do you keep retro actions from evaporating? Do you track them like normal work, limit the number, or something else? And what's an action item you've seen that actually changed something?