r/deltek • u/CosmicHipster32 • Aug 29 '26
Cobra Task Usage and Resource Usage View
Hey guys,
Our company recently transitioned to OPP, Cobra, and PM Compass.
We were previously using Microsoft Project, and we have a monthly report that pulls together all program demand by resource, and allows us to pivot that data in excel to generate a report.
It was critical for us that we use the Microsoft Project Resource Usage and Task Usage views so we could see how much each program asked of each resource before we pushed that out the system. The resource usage view in Microsoft project allowed us to see and tweak the hours by resource on a monthly basis before we published that demand.
Do you know if Open Plan has anything similar? Essentially a view that time phases resource demand on a specific program and shows how many hours are forecasted each month? Bonus points if it shows the tasks and hours in each month as well.
Thanks guys!
2
u/ChickPilot1 Oct 07 '26
There are a couple ways to solve this. Remember, tasks, resources, and relationships are each held in separate tables. Look for a spreadsheet view that pulls Resource/Assignment or Assignment/Resource. But that won’t give it to you timephased. Another way is to configure a Cross Table report from the Export ribbon.