r/developersIndia • u/bijliwala Researcher • Feb 08 '24
Tips How do you reply when your manager asks : kitane time mai ho jayega ( in how much time it'll be done )
I was asked by my manager yesterday ke " kitane time mai ho jayega " ( in how much time it'll be done ) , I simply replied " jitane jaldi resources de doge utane jaldi " ( the more fast you give resources the much fast ) .
What are the kind of replies you have given .
Ps : if you're a manager, how'd you reply to such answer.
376
Upvotes
312
u/AnInsecureMind Feb 08 '24
I'd be a bit put off tbh if o got such a reply. The reason I'm asking you is that I have to give ETAs to the business and other stakeholders, and I thought I can rely on your estimate + some buffer to do so. But 🤷♂️ that turned out to be non helpful.
288
u/dhrjkmr538 Feb 08 '24
he is asking an estimate, so reply him 1.5 X what you think, keeping that you work in office hours and take proper breaks.
68
u/sangramz Feb 08 '24
This is my standard reply:
This has been my proper reply since I have got prototyping 60-70% of the time.
20
u/red_jd93 Feb 08 '24
If I know what needs to be done, i just around double it, or reasonably give enough buffer, as manager adds a bit more buffer anyways. But if I have no idea what is happening (that also happens sometimes) then I straight up refuse to give timelines.
121
u/SilentGuyInTheCorner Feb 08 '24
Never answer that question with an absolute number. It’s a trap.
44
u/NoProfessor8897 Software Engineer Feb 08 '24
take 20 percent or 10 depending ur knowledge on stuff buffer divide task and get ETA and do everything written in mail so that they wont force in u future
55
u/TumbleweedRough8219 Feb 08 '24 edited Feb 08 '24
Ab jitna time lagega utna lagega naa lawde
66
u/wavereddit Feb 08 '24
If it takes 5 days, double it and say 10 days. And after a few minutes of intense thinking, double it again.
20 days.
There you have your accurate estimate.
11
u/mihirshah0101 Data Scientist Feb 08 '24
thats a vague reply with no meaning... you can get an estimate of what time you think it'll take
add ~25-30% time there depending on no of days and then report that as a time range
the reply you gave was not conclusive and did not answer the question
even if you need resources you can give a time range with some buffer and then follow up with the request of resource in interest of expediting the process.
11
u/musicplay313 Feb 08 '24
Underpromise, overdeliver
15
u/slackover Feb 08 '24
Multiply what ever you are going to say by three
5
u/le_stoner_de_paradis Self Employed Feb 08 '24 edited Feb 08 '24
By finding next job, there is no remedy for these sort of people.
I usually try to explain them the time required and why it's required, but if he/she start comparison or try to push too hard, I agree, provide crappy Workable increment, and then leave the team with low QC things in their hand.
And now from I leadership positions, when I am responsible for atleast some increment, I generally learned from my life and how me and my team members used to add buffer time, I call everyone for a meeting, ask everyone how much time is required, how we should do it, and I know we all are human so I do addition of buffer time from my end for the entire team.
See, Transparency is required with your Leader because they need to answer as per this, But if your leader is dumb and trying to push everyone hard for his/her benefit without understanding others benefit and leave, because once team members leave first of all production will get impacted for a few days, also crappy code reduces velocity of the product and include cost of qualities like technical debt, so if your manager is a creep give him back what that person deserves.
If he is good,
Try to negotiate timeline, explain why it's required, like I came to product and IT from a civil engineering background, so during my first 1 -1.5 yrs I have learned many things from my peers and managers, even when I first started as a TL Learned from team and I am still learning. But I always make sure to make everyone in the team feel comfortable even though I am the one who asks annoying basic level questions like a school kid, because my forte is business and I share those knowledge with people in tech. So we have mutual respect, try to create it.
2
u/No_Savings_891 Feb 08 '24
Always double the number n reply, never answer like this ever. Experience hai my manager was put off once.
2
u/phoenix_93 Feb 08 '24
Jab hoga tab pata chal jayega :p
2
u/reignofchaos80 Feb 08 '24 edited Feb 08 '24
If things are clear, follow as everyone says here. If things are unclear, due to XYZ reason, it is best to give a date for a date. You may say I can't estimate right now but I should have an estimate of due date by date ABC.
This buys you time to get an absolutely clear picture and you should be able to commit to a reasonable timeline and a formal deadline in peace.
I follow this and this has worked while I was a dev, while I was a manager and now when I'm a manager of managers.
2
u/[deleted] Feb 08 '24
best reply is, let me get back to you
if pushed to give a number immediately, give it with the condition 'that's off the top of my head, not something I wanna commit without assessing"
2
u/halidon2k Feb 08 '24
I always exploits agile process. Jitna story point utna time 😎
2
u/kabirasani Full-Stack Developer Feb 08 '24
Every time you have to give a deadline in a corporate setting, here’s a simple mantra — Underpromise by 15%, Overdeliver by 10%.
There is a reason for those specific numbers.
15% underpromise would mean you get enough buffer time to accommodate unknowns. If a task has an unknown factor > 15%, the task is not ready to be worked on yet.
10% overdeliver would mean you deliver precisely at the time it is expected to be delivered. You meet expectations. Just know that meeting expectations regularly = exceeding expectations towards the end of the quarter. And exceeding expectations regularly = burn out.
Pick your battles.
2
u/Tough-Difference3171 Feb 08 '24
What you answered, should be mentioned after giving a plan of work estimates, and the man days required.
That's when you can say - "I need 2.5 people's 1 month worth of effort. Ab jitni jaldi reqources available karvaoge, utni jaldi kaam shuru ho jaega."
If I was the manager, I would ask:
"Kya resource chahiye?" (Log chahiye? VMs chahiye? Subscriptions chahiye? Ya Nirmala Sitaraman chahiye?)
"Kal 5 bande de du, to parso kaam ho jaega kya?" (Soch le, nahi hua to kand mar lunga)
"Khopadi ke, cool banne me burai nahi hai. Lekin pahle kaam kar lo, fir cool banna."
Btw, I am not a manager, and don't want to be one.
2
u/kinkshamer25 Feb 08 '24
ALWAYS UNDER PROMISE AND OVER DELIVER. any other answer is going to get you under more pressure
2
u/lusty_vampire Feb 08 '24
well tbh it depends on his 'tone' basically, My RM used to delegate me work with a 'superiority complex' like abhi adhe ghante me kr k de. And i being me always used to take my sweet time with it, no matter the urgency. On the other hand if my dept. Head asks me to get a work done (he's very soft spoken), i get it done within the time frame of not before. See, INIDAN CORPORATE culture should understand this, no one is anyones slave or at your disposal. Give respect take respect. I mean that's what i do and what I follow as an ideology.
2
u/DirtDramatic7065 Feb 08 '24
Your manager is just asking for estimates since he also has to present these estimates to leadership for project planning purposes, nothing wrong in it. If you know the estimates, you should share that and if you don't know it then you should give a DFD (Date For a Date) which means you'll share the estimates on that date.
2
u/FanneyKhan Feb 09 '24
Please please please stop being a dank memer in your office! An estimation is something anybody will ask you.
If you’re working on uncharted territory, take some time to come up with an estimate. Break down the problem statement into smaller parts. Come up with “clear”, “sort of clear” and “unclear” tasks.
If tasks are clear, you should be able to estimate it will take X folk hour. Mark it up by 1.5X.
If tasks are sort of clear, assume it will take you Y hours to do the task. Mark it up by 2x.
If the tasks are unclear, read more. If you still can’t give out an estimate, break it down further and give a timeline of how much time you will take to get to familiarity and then do the first two points once you’re in familiar territory.
If you take a day or two to come up with an estimate, that is fine. You can even come up with a timeline based on how many resources. “Give me X resources, I’ll take Y days.”.
If you tell me the answer that you told, I’ll probably give you 5 people and ask you to deliver in 2 days 🙂
2
u/JeenaIsiKaNaamHai Data Scientist Feb 10 '24
Always remember: "Underpromise, Overdeliver"
Let's say you estimate it will take 2 days to complete the task. You inform your manager that you'll need 3-4 days
4
u/[deleted] Feb 08 '24
As a manager I will not ask, I will set the deadline. But I will ensure they have enough buffer to complete and also have the tools needed to finish.
1
u/rahem027 Mar 10 '24
Say, "I am not really sure. These are the things that might cause problems. If everything goes well, X days/weeks/hours. If all hell breaks loose, Y days/weeks/hours. But I think it should mostly be done by Z days/weeks/hours +/- a reasonable buffer"
1
u/Aadamkhor Feb 08 '24
You could reply that it will x days from the day you start with y number of resources. provided that the resources are of a particular skill level and by a particular date.
Also add from.your previous experience if he needs to add buffer to accommodate for any requirement changes and rework.
1
u/piratekingsam12 Feb 08 '24
I get it that they need to give estimate but software development is lind of like research in many ways unless you're doing a routine task and it gets really difficult to estimate 😅
1
u/loudlyClear Full-Stack Developer Feb 08 '24
The reply is quite offsetting because if the manager gives ETA without your consent then also that'd be a problem when the manager asks you then also people turn defensive.
Ps: Concerns related to the project could have been handled in a different way ... I guess like agr resources hote mere pas then I would've commited it by this time but since we don't have any this could be the estimated time.
1
u/flight_or_fight Feb 08 '24
There are standard ways to estimate effort.
If any of my team members told me this - I would take them off the project and ask them to prepare for interviews ASAP.
1
u/ay230698 Feb 08 '24
Effort wise x days/weeks etc as per the current view
Expected blockers from abc which I cannot confirm until I discuss with them.
I will update you as I get more clarity on my end.
1
u/[deleted] Feb 08 '24
Apko kab tak chahiye? ..then if he blurts a time..u say 1.5× to 2x of what he said..never commit to numbers first..salary/time etc
1
u/Amazing_Theory622 Web Developer Feb 08 '24
Divide the task in parts, give slightly delayed estimate for the first part and say that whole task estimate will be given based on how much time the first part will take.
1
u/vinayk7 Feb 08 '24
Chad reply !
1
u/bethechance Senior Engineer Feb 08 '24
Design+Development+Testing+Buffer(very important)
1
u/DuckSleazzy Fresher Feb 08 '24
"Deadline tak"
1
u/webkrsna Feb 08 '24
Me: clearly reports the work done and pending work. Manager: so what is the eta for the pending job. Me: if you want I can put it in priority and start working on this. Manager: so can we finish in next 2hrs. Me: will report you the update in next 2hours. Manager: ok
1
u/aonboy1 Feb 08 '24
I just divert the uestion to know why is my mananger asking me to give n ETA. It goes somwthing lile this : -
**I feel it shall take "X" days/hours but, let me just recheck and get back to you for any potential anomaly. Are there any urgent deadline Or client dependency with this task? **
1
u/TribalSoul899 Feb 08 '24
Calculate a quick estimate and tell him. 2 hours, 10 hours, 2 days or whatever it is. Mention that it’s only an estimate and you’ll let him know the exact time shortly. Then deliver that work before the time you promised.
1
u/haridavk Feb 08 '24
you need to estimate the amount of work it involves and from that be able to make a good guess on the reasonable time it takes. its, also prudent to list the resources you need, by when and for how long.
just throwing an absurd response back at him will only invite a similar response later...
when will i get a raise? when you deserve them.
1
u/AstronautCharacter89 Feb 08 '24
I generally give estimate in Man Days ( taking 6 - 8 hours as standard) along with estimates of best- likely - worst. So, if a task has to take 36 hours, it will be 5-8-12, with 5 Man days best case scenario.
1
u/doflamingo0 Feb 08 '24
ask him for 5-10 mins, then break down task into sub tasks and estimate each sub tasks, then show him the estimate. In this way if some things gets added later you can alwasy show it was not part on initial requirement and then take more time for it, alwasys add some buffer time for r and d
1
u/chacha_tera Feb 08 '24
Rule of thumb is: consider the worst case scenario and then double it.
1
u/moab911 Feb 08 '24
Its better to give a correct date and be Frank in case he asks to get it finished on same day and if it is not possible
1
u/[deleted] Feb 08 '24
Give 2x the time, finish in 1x, give in 1.5, if manager thinks I'm slow I can optimize accordingly.
Basically underpromise and overdeliver
1
u/AllanSDsc Feb 08 '24
First of all, you should know the answer yourself! Break down your projects into components, modules, etc. Place hours / days in a private worksheet or similar tool next to all these. Put more time for higher-priority aspects, or where more research will be required if not done before. Also consider resource dependencies, and keep reasonably substantial buffer.
Next, add all the hours & days up, so now you have an estimate. Before presenting to your manager, add some more topping buffer 🧁S/he might say ‘Its too much time!’ or ‘It shouldn’t take so long!’ or ‘Really? Are you sure about this?’. But you stand your ground for now.
Now, it depends on how much pressure s/he is getting from superiors. If s/he does have this, s/he will angrily & loudly say ‘You have to reduce this estimate under any circumstances!’. So, now you remove that topping buffer, but don’t tinker too much or at all with your original buffer. Stand your ground.
S/he might keep a daily or maybe even a few hours track of your progress. But you, being a true techie, haven’t fooled yourself and will most surely complete it within your estimate, not counting emergencies.
1
u/samuellawrentz Frontend Developer Feb 08 '24
Double it and give to the next person..
1
u/SnooDogs6511 ML Engineer Feb 08 '24
This is something I have had problem with, a lot. And sometimes I have nightmares. For a person with OCD, this can really be the worst, so I guess you gotta just: (a) know the folks. how the system functions there. look around, observe (b) as others suggest, include some buffer. But don't spend too much time thinking about this.
1
u/Omkara7 Frontend Developer Feb 08 '24
I didn't get a chance 😔
1
u/Venmoira Feb 08 '24
My honest reply to my manager was "Pressure daaloge toh gu milega."
1
u/Zakirk93 Feb 08 '24
Once manager said "ye to 5 min me ho jata hai" I said on floor "aap 5 min me kar do me apke pero k beech me se nikal jaaunga"
Haha whole floor was laughing
1
u/[deleted] Feb 08 '24
It's more of a chemistry between you and your manager and how many much knowledge he has related to task. I prefer to say actual time I need. I should be able to finish comfortably in that time.
1
u/AweShadySome Feb 08 '24
If you know what you have to do and if you're good at it, you will have an estimate of how long it'll take. However, factor in exigencies and other hurdles and give a realistic timeline. keep an 8-10% buffer for rework and final delivery.
1
u/prakulwa Feb 08 '24
I give twice of estimate
1
u/justbsaiyan Feb 08 '24
When I had a job, I'd respond stating 2x the time it would take. Then I lost my job.
1
u/[deleted] Feb 08 '24
I would've peed on his carpet in order to assert dominance. It's a classic, I've seen primates doing it all the time.
Note: The jungles don't have law and order, so do this at your own risk.
1
u/Sufficient_Abies_469 Feb 08 '24
Dekho sir, pahle to time schedule karna padega, fir ek proper excle sheet pe time line banani padegi, work flow discuss karna padega tab jake pata chalega.. Senior: ye sab me kitna time lagega? Sir kam se kam four days.. Senior : to ye sab ke bina kitna time lagega? Sir kam to Sirf 3-4 hours ka hai..
1
u/abhitooth Feb 08 '24
Bache ka paida karne me 9 month to lagte hi he.Ye toh ek task he toh aap dekh lo.napne hisaab se calculate kar lo. Baki me toh available hun.
1
u/naaina Data Analyst Feb 08 '24
The art of estimation is something to be learnt ..never forget to have a buffer added to it
1
u/ady620 Frontend Developer Feb 08 '24
Always ask for time to do analysis before giving any estimation. Always give an estimate in story points. Never give an estimate in hours (use days if possible). use the word atleast if you are unsure.
1
u/FunctionDull2648 Feb 08 '24
If my manager asks for the deadline of the whole projects which generally takes 2~3 months, before even design discussions begin, how should I reply them? Seems like most of the comments are for small tasks
1
u/flutteringdarts Feb 08 '24
He asked kitne done m data bhejnna h I said ek hafta Tak bhej denge
Fir looks dia toh 2 din bolna pada
1
u/MaddySPR Feb 08 '24
Only tell the estimation time after you know what was the issue, so first just ask time for find out the rout cause then give your estimation 😁
1
u/Niagr Feb 08 '24
Always reply with a best case and worst case. If you can't come with best and worst case, break the problem down further, or ask for some time to prove our the complex portion (called a Spike in agile terminology).
1
u/Significant-Tear-560 Feb 08 '24
😅😂🤡
1
u/gsah796 Feb 08 '24
Just ask him how much time you will take to do the work? And just multiply it 1.5 times as your manager has experience ... If it's reasonable time it's okie .if he's gives to little time just tell him can u show me by doing this work in your expectated time
1
u/Optimal_Estate5112 Feb 08 '24
Your reply is fine. Just quantify it. Jaise - Suresh kal free ho raha hai, par Ramesh Friday tak busy hai to with that capacity, next week Thursday EOD Tak (when your estimate is Tuesday). If Suresh or Ramesh are getting busier than expected, revise your timeline immediately. Manager will have to revise expectation or take something off the team's plate. Data loaded responses help in making your personal brand as well, and showcase how good a control you have on your team.
1
u/AshamedNegotiation92 Feb 08 '24
I always say this is my estimate, even if it is a small work, I never commit to the timeline myself.
Manager/Client: How long will it take to complete task A?
Me: If everything goes right, I think it should be completed by EOD, but if I face challenges time could be extended.
This is my format of reply 100% of the time, although 90% of the time I adhere to the estimate. The 10% of the time I don't adhere to the estimate will not affect my credibility as I always do mention the reason for the delay. Communication is key to have a good rapo.
1
u/prtk297 Feb 08 '24
Being a manager, let me give a managers perspective.
He is not just asking for the heck of it. He has to commit to someone as well with timeline.
If you give such smartass answer manager knows he can’t rely on you.
Give an estimate with buffer if you have to. A good manager will add his own buffer when he communicates deadline forward.
One more thing to add, if you give these smartass answers manager will not hesitate to throw you under the bus. But if you are cooperative, good manager will go out of his way to defend any timeline slip ups.
1
u/[deleted] Feb 08 '24
feels like saying - aye chal na madar**od apna kaam kar. Fir dhyan aata hai, yahi to iska kaam hai. I double the estimate and tell him.
1
u/MidnightDream11 Feb 08 '24
I ask this question to some and I answer this question to some as well. So I can very much confirm that's a shitty and stupid reply. You're only putting yourself in a vulnerable position trying to be over-smart. Just say, 'This would take x person-day of effort, with 5-10 % margin. That'd put the ball in his court. When he allocates resources, pd effort counting starts from that point of time and you are safe.
1
u/Wide-Market-6306 Feb 08 '24
Mera boss sirf ek hi line bolta hai. 10 min mein ho jayega. Sara data to ready hi hai….
Uffff
1
u/Brown-Mr Feb 08 '24
I'll review the requirements and update you on the it ASAP
1
u/The_LostPilot Feb 08 '24
Just say it: Ek hi din main baccha paida nahi hoga
1
u/The_LostPilot Feb 08 '24
Just say it: Ek hi din main baccha paida nahi hoga
1
u/onceuponatime_24 Feb 08 '24
There is no right answer. In my experience, if I give a low estimate without a buffer, I almost always fuck up because some or the other error pops up unless I am working on something trivial. So then I started giving him the time with some buffer added, so he tells me this is such a trivial task, there is no reason for this task to take so long🥲.
Dude it's trivial for you because you have been in the industry since I was in high school. I just joined half a year back, how do you expect my level to be even half yours
1
u/__gg_ Feb 08 '24
I'll get back to you in 10 mins
1
u/thebiasedindian1 Data Engineer Feb 08 '24
Like others suggested, break the task into subtasks and estimate those. Taking 1.5x as buffer is also fine. I have been in this situation often where the path is not clear. I usually mention a "testing-UAT-data_sanity" and CR for an avg of 1week to the main task. Later on I may need more time in main task and rush through testing in that week or deliver earlier(rare coz some or the other HP request comes in betweena sprint). Corporate works on "under promise, over deliver".
1
u/1BrokenPensieve Feb 08 '24
Reply can be like- By when do you need it done?!- Deadlines are always to be set by the manager in order to have a fallback when things go kaboom.
1
u/Abhimri Feb 08 '24
I'll say I don't speak hindi, can you please clarify what your question was.
1
u/iceberg_1001 Feb 08 '24
A senior dev gave a estimations mantra, 1 is your original estimate to get the thing done +1 for testing +1 for documentations and emails replies and +1 for showing you actually worked on this.
1- is your estimate of getting that work done.
P.s.- this one is primarily only for service sector IT jobs. (I guess)
1
u/[deleted] Feb 08 '24
1.5x the time I can actually do it in, and then double it.
1
u/raultoks_ Feb 08 '24
why is communication so hard, what happens if you give him a soft deadline, saying hopefully can be done within this but might take more time.
1
u/zerokha Software Architect Feb 09 '24
Your answer is really naive, all estimates are about total time needed to complete a task irrespective of the resources involved. So you have to give days in terms of development time. Better to divide it in design development back end ,development frontend, qa hours of time. Now it’s upto your management stakeholders how fast they want to complete it and deploy resources.
1
u/Environmental_Today2 Feb 09 '24
1
u/Environmental_Today2 Feb 09 '24
1
u/pps96 Feb 09 '24
The best answer is “it depends …”
1
u/I_mkul Feb 09 '24
Generally I'm the one who knocks ( means I'm on the side where they ask questions to subordinates) 😄🤣
1
u/[deleted] Feb 09 '24
Respond with: "In how much time it will take to teach you common sense" 🙂
1
u/Intelligent-You2158 Feb 11 '24
I am a manager and have seen my devs struggle with estimate at times like these, best thing to do as per my experience is creating a tech discovery ticket for 2 to 3 days. Post that you will have some level of clarity on areas which can be started and their estimate.
1
u/FuzzyCraft68 Data Engineer Feb 11 '24
I used to work in the office until I moved far and started working remotely. My manager calls me as if I am his boyfriend. I used to receive calls in the beginning but started avoiding them. Now he sends me texts and waits for my reply. But just to ask how much time would it take?
I told him that it would take 2-3 hours and usually, I would be done with work in the next 15-20 mins. I do this because that asshole tries to make me work 24/7 but I am certain that he can't fire me.
1
u/Opening_Equipment_45 Feb 12 '24
If you can complete that task in 2 days, then tell your manager it will take 3 days, it's a rule in corporate.