Other How long do you keep running mining equipment when it starts showing signs of trouble?
I find it frustrating when a machine starts making unusual noises or showing signs of wear, but the decision is still to keep it running because production can't stop. I understand that downtime affects the whole operation, but surely dealing with a small fault early is better than risking a major breakdown later. A few extra hours of production might not be worth the repair bill or extended downtime.
0
Upvotes
•
u/AutoModerator 14d ago
All comments must be civil, productive, and follow community rules. Intentional violations of community rules will lead to comments being removed and possible bans, at the discretion of the moderators. Use the report feature to report content to the moderator team.
I am a bot, and this action was performed automatically. Please contact the moderators of this subreddit if you have any questions or concerns.
33
u/G-bucket 14d ago
Run it till she blows hardrock mining
13
u/DSM202 14d ago
Frustrating for those of us that do the fixing yes, but it’s often worth it in the big picture. 6 hours of downtime to do a repair before the problem gets bigger instead of 2 days to do a bigger repair might make sense until you see what they would have made in production during those 6 hours. You schedule that 2 day repair for a shutdown, when you’re down anyways to do other work.
18
u/Ruger338WSM 14d ago
Spoken like someone who has never been in a mine maintenance role. Operations and Maintenance have different KPI’s, if only your hypothesis were true. Caught on a PM the cost is X, schedules itself 10X, depending on the mine and plan it could be well worth the bill. Run-to-Failure is a time honored tradition in the mining game.
6
u/Hangar48 14d ago
When you stop production, you're not looking at just this machine but a whole chain of events. It can run easily into hundreds of thousands of dollars per hour.
7
u/mancin 14d ago
do you work in mining, why ask such a vague question?
3
u/Square-Print1453 14d ago
You should have a good maintenance planner, competent users and a good regular system. Just kidding, breakdowns are frequent, frustrating and normal, just got to hope you get a decent run out of them - or lease, so you can swap them out. Also, try to swap out the bad operators who flog them. 😵💫
3
u/justinsurette 14d ago
24volt reset,
Safeties shut it down or fire,
2
u/SlitherSnakeZ28 14d ago
19 year old underground hard rock miner here. The guys like to give me shit for breaking things because of my age so anytime I hear or feel something going out I always call in the mechanics and have them tell me what to do. Usually they say keep running it and we’ll fix it if it blows up so I make them initial that on my pre op
2
u/ltek4nz 14d ago
Get workshop on the 2way. Get verbal OK to keep running. Give it til it gives up. Then when it breaks down it's workshops fault. 1 hour downtime on my shift to fix it is a company loss of $1m
1
u/Ratchets-N-Wrenches 14d ago
Tbh it’s because of production yes but it seems like it’s primarily downward pressure from
Higher and higher up, distorted performance metrics, bad communication, lack of understanding and greed. The people calling the budget shots aren’t always part of the same budget (running repair vs PM vs scheduled downtime) or the same team. They’re above your boss and your boss does what they say, they don’t know or understand the point of short periodic stops vs major breakdowns because they’re only looking at numbers and how they impact their metrics that they’re held accountable to.
Additionally it’s often a risk vs reward aspect, often nothing comes from ignoring the small issue so many times that it’s “unexpected” when the repeatedly ignored small thing becomes big because they don’t understand the system.
As a tech I agree, why not down it now for a few hours or days vs later for weeks but we don’t play by the same rules or with the same understanding as those people making those calls.
Most mines or operations sadly run this way to a degree and often don’t “budget” for unexpected outage of any sort so if their hand is not forced they don’t do it
1
u/GovernmentWide7151 14d ago
I hope you do defect elimination and proper RCA, which can help understand the nature of the failure modes so you can diagnose them better. prosolved.io Start here which first understanding your problem and its impacts, then develop the right actions. This is the full methodology for iso55001
1
u/Enigma_Custom 14d ago
I have a piece of plant or equipment that makes 100k an hour. I have a failing gearbox that will take 3 hours downtime to replace and will save the gearbox from destruction or there's a window in three days where it's planned to have 1 hour downtime any way but we'll destroy the gearbox. The second option makes us an extra 80k. It's experience and calculated risk.
1
u/Substantial_Knee_275 12d ago
If it's an apron feeder, until the chains crack or stretch so much the take-up cannot be tensioned any further... Until the chain pins are cracking or creeping out... Until it's shearing pan bolts and spitting pans.... Until the rollers are seized or fouled and torn away from the chassis.... Even then, if it'll still rotate and run product then she can bloody well wait for her next scheduled overhaul!
1
u/kajukembo 12d ago
When it gets to this point, it comes down equipment criticality. Running equipment to failure that is identified as a single point of failure is a different take. Granted, if there were signs of wear and tear for much time before it runs to failure, I’d wonder what the PM schedule is for that specific equipment, or if having peripherals such as temp and vibration monitoring can help with predictive maintenance.
1
u/Stanthemilkman8888 12d ago
Yeh it’s called preventative maintenance. Do it in the shut down. What kind of maintenance planning software ware do you use?
1
u/kurtdb16 12d ago
Till MSHA shows up and red tags it.
1
u/Psychological-Cow-28 11d ago
Run it until the wheels fall off... Literally in some cases.... I'm looking at YOU Freeport Mcmoran Morenci 👀
1
u/AdvanceAdvance 11d ago
Math is not strange, straight Quality Is Free books stuff.
As a machine goes out of spec, how much to take it offline versus how much to have a failure. You get odd economics arising. For example, taking down machines in batches to minimize downtown while doing preventative maintenance. Also, run the machine to death because downtime costs too much given production penalties and the machine won't be any faster to replace.
In an ideal world, one orders all the parts and gets maintenance people ready, then shut down for a very short window to replace "whatever you can get done in one shift".
1
u/Extension-Note4173 10d ago
As a mining mechanic, their favourite trick is instead of fixing a minor problem that could be fixed quickly, is to wait for a catastrophic failure that will take 3x as long to fix, and cost 10x as much.
4
u/2point8s 14d ago
Fitter got a copy? "Yeahhhh rodgy"