r/primavera • • 5d ago

Help— Update Progress - Process Confirmation

Long story short, I’m working in a portfolio of projects. So, I have a master few master schedules that require updates from multiple contractors in each (procurement, construction (2), commissioning). My schedule has all activities, theirs has only ones pertaining to their work, but all their schedule activity IDs are the same as mine.

Can I add their weekly XER as a baseline, and create a few Global Change (GC) functions to update the activities in the master schedules?

I.E: I add their schedule as BL1 and create a few GC actions.
For Activities-
Status = BL1 Status

If Status = In Progress
Then Actual Start = BL1 Start and
Expected Finish = BL1 Finish

If Status = Complete
Then Actual Start = BL1 Start and
Actual Finish = BL1 Finish

For Resources/Units-
Budgeted Units = BL1 Budgeted Units

Actual Units = BL1 Actual Units

Remaining Units = BL1 Remaining Units OR I might create a UDF with a GC to make Remaining Units calculate (budget - actual = remaining) and then make the Remaining = the UDF (since P6 sometimes gets this wrong).

Brainstorming with professionals because AI doesn’t know schedules like humans do.

5 Upvotes

5 comments sorted by

1

u/tale_of_tejon 5d ago

Why not import a spreadsheet of their status into your XER?

Note, the spreadsheet needs to be formatted a specific way. You can find out more online. But that how I do what you are explaining… at least my understanding of what you are explaining.

2

u/TipMurky1893 5d ago

I was trying to do it that way, as that is how I’ve done it in the past, but… when I import the XLSX not all the activities are being updated correctly and it is driving me NUTS!

Our database is on a server provided by a consulting company. They say I have all the permissions open, but to let them know what else I need and it’s hard to know what I need before realize a function isn’t working. Trying to analyze the errors and what updated vs what didn’t, catch and correct is just a brutal as updating it all manually. 🫠

3

u/That-Second-1333 5d ago

Give all the xers to cloude and ask it to update them for you it works perfectly

1

u/jbrbg 3d ago

Have you tried the XER/xml approach yet? I would have thought p6 would not allow import/update to the master project because the guids, project id & wbs would all be different.

If you're just trying to get updated starts/finishes then the xlsx approach is pretty sound, provided you can figure out what is causing your errors, that can be tricky.

Updating units is a bit more involved, the percent complete types of the activities matters a lot. Units are usually at the resource assignment level (unless there are no resources assigned) not at the activity level. If you have activities with multiple resources it can get complex really quickly.

Years ago, before LLMs and even the advanced features of Excel I built a database & queries that would create an XER for me. It worked well, I am sure it's much easier today to build an XER from other sources, as suggested by others.