r/projectmanagement • • 20d ago

EVM

Unpopular opinion: Earned Value Management (EVM) is overrated, and the industry needs to seriously revisit, reassess, and recalibrate how we use it.
We have become obsessed with CPI, SPI, and earned value percentages, as though they reliably reflect actual project health.
But here’s the uncomfortable question: Can a project report excellent EVM indicators while its critical path is deteriorating, productivity is declining, and its forecast completion date is slipping? Absolutely.
EVM measures performance against a defined baseline, but it doesn’t necessarily tell us whether the project is truly progressing toward successful completion.
A healthy SPI doesn’t guarantee an achievable completion date. A favorable CPI doesn’t necessarily mean the final margin is protected.
Perhaps it’s time we stopped treating EVM as the gold standard of project performance and started placing greater emphasis on schedule integrity, critical path movement, productivity, forecast reliability, and actual completion risk.
My question to fellow planners and project controls professionals: Are we measuring project performance, or are we simply measuring how well our reporting formulas look?
EVM still has value. But perhaps we’ve given it far more authority than it deserves.

9 Upvotes

45 comments sorted by

4

u/cryptopindar 20d ago

Sorry if I offended anyone here. That was never my intention. Just sharing thoughts and encouraging some healthy debate. We may disagree on methodologies, but at the end of the day, we’re all professionals learning from each other. No hard feelings. Love you guys! 😂❤️🍻

1

u/christan_Thurton 19d ago

all good man, half the value of this sub is debating stuff like this anyway

2

u/SVAuspicious Confirmed 20d ago

Can a project report excellent EVM indicators while its critical path is deteriorating, productivity is declining, and its forecast completion date is slipping?

No. If you're seeing that you're doing something wrong. Most often the work that's actually being done is not what is in the baseline and people are reporting as best they can because 1. they have to and 2. they don't understand the implications.

Your formatting suggests AI. Even if you wrote it yourself, perhaps you've become too dependent on software and have lost sight of actual methodology.

If you have a project off track as you describe and it is not reflected in CPI and SPI it's you and the project, not EVM. I've found that (context: turnaround PM, I walk into dumpster fires on purpose) one easy way to identify that is to calculate and graph EVM CPI and SPI at the task level or one level up in the WBS (depending on task size) and look at variation (just look at the graph - no additional calculations). If it's all over the place from very low to very high that's an indication your baseline doesn't reflect work that is actually being done. Another indicator is not collecting individual timesheets. Management estimates based on assignments are not good enough for anything much less EVM.

"You're off the reservation, mate."

0

u/cryptopindar 20d ago

Yes, it's AI-assisted. The thoughts and technical arguments are mine. I simply use AI to structure and articulate them better. I don't see anything wrong with using modern tools to communicate ideas. But let's focus on the engineering rather than the formatting.

I actually agree with several of your points, particularly the importance of baseline integrity, accurate progress measurement, and analyzing EVM at the activity or WBS level.

However, you're assuming that properly implemented EVM will necessarily capture critical path deterioration through CPI and SPI. That's precisely what I'm challenging.

Let's consider a simple scenario.

A project has an SPI of 1.10 because substantial noncritical work is progressing ahead of its planned value. Meanwhile, several activities on the driving critical path are delayed, extending the forecast completion by 30 days.

This isn't necessarily bad reporting, an incorrect baseline, or poor methodology. It's mathematically possible because traditional SPI measures earned value relative to planned value, not the time sensitivity of activities within a CPM network.

Even calculating SPI at the activity level doesn't automatically establish the impact on project completion. You still need CPM analysis to understand driving relationships, float consumption, critical path migration, calendars, and the resulting completion forecast.

And CPI? A project can be performing efficiently against its earned value while still facing significant future costs from delays, prolongation, or disruption that have not yet materialized in actual costs. That's why credible ETC and EAC forecasting matters.

Your recommendations improve EVM implementation, and I agree with them. But they don't eliminate the fundamental distinction between cost-weighted performance measurement and network-based schedule forecasting.

My argument isn't that EVM is useless or that practitioners are implementing it incorrectly. My argument is that EVM should not be treated as a sufficient standalone indicator of project health, regardless of how well it's implemented.

And if your response is that EVM must be supplemented by CPM, resource analysis, productivity tracking, and independent forecasting, then we actually agree on the central point.

That's exactly why I believe the industry should reassess how much weight it places on EVM indicators.

We can debate the methodology without questioning whether someone used AI to express their thoughts.

1

u/SVAuspicious Confirmed 20d ago

If you need artificial tools to communicate effectively your "thoughts and technical arguments" aren't worth much.

And if your response is that EVM must be supplemented by CPM, resource analysis, productivity tracking, and independent forecasting, then we actually agree on the central point.

If your central point is that software (e.g. AI) can't do your job for you and you need to know what you're doing than we agree. I doubt that's the case. You completely missing the integration of what you're treating as separate methodologies.

I judge people who need another entity, computer or human, in order to communicate and make a case.

You realize the error rate of AI is 30%, right? I wouldn't take that from a person. I won't take it from a tool.

3

u/ZodiacReborn 20d ago

Shoot do you have a source on that 30% number? I was just arguing with our data analytics director this morning about AI error rate and that'd be a delicious factoid.

1

u/SVAuspicious Confirmed 20d ago

I plowed through the peer-reviewed material on Google Scholar a few years ago and updated about two years ago. Very complex search term like 'error rate of AI.' If you're going to use it, it's due for an update. Please report back. You have to weed out the vested interests.

The post and comments of u/cryptopindar are material for examples.

The biggest problem I believe with AI is the training material. People say all sorts of things, much wrong. AI digests that and spews it back out. Other AI sucks it in and spews that back out. The net is dumbing down.

Error rates vary across domains and versions. In healthcare, rates ranged from 8% to 83%. Business and economics saw error rates drop from ~50% with GPT-3.5 to 15-20% with GPT-4. Engineering tasks averaged 20-30%. Programming success reached 87.5%, though complex debugging still showed over 50% errors. In SE, requirements and design phases showed lower error rates (~5-20%), while coding, testing, and maintenance phases had higher variability (10-50%). Upgrades from GPT-3.5 to GPT-4 improved reliability.

source: https://arxiv.org/abs/2504.18858 dated 2025 at the top of a quick look at Google Scholar. There are some big numbers in there and nothing to be proud of. Any of those would get an employee fired.

1

u/ZodiacReborn 20d ago

Cheers sir! That was comprehensive.

1

u/SVAuspicious Confirmed 20d ago

I'd look at more papers (that's what I did the first two times) and do more meta analysis, but that one paragraph on a slide is telling. Needs proper citation from the link for sourcing. Don't give them the link. Make them dig.

Best of luck with your analytics director. Frankly, the concept of someone leading (presumably leading) analytics fighting to turn his or her entire job over to AI is the height of irony. The movie Idiocracy is truly a documentary.

0

u/cryptopindar 20d ago

Genuine question, can you point out exactly where the error is in my post or comments? I’ve read them again and can’t find what you’re referring to. I’m open to correction, just curious how you arrived at that conclusion. Cheers!

1

u/SVAuspicious Confirmed 20d ago

Errors in fact about EVM, assumption that variables are independent when they are in fact highly integrated and mutually dependent.

Note the error rates of AI cited above and do your own search in Google Scholar.

Again, software can't do your job for you. You have to know what you're doing. That your review did not find the AI errors indicates that you don't know what you're doing, at least in the domain of PM metrics.

2

u/cryptopindar 20d ago

But where exactly did I say those variables are independent? I specifically highlighted CPI and SPI because they’re commonly used performance indicators. I never claimed EVM isn’t integrated with other project controls methodologies. You’re challenging an assumption I never made. I’m simply asking which specific statement is factually incorrect.

1

u/SVAuspicious Confirmed 20d ago

We now know you haven't figured out how to edit a comment and just pin another one in. Divide and conquer doesn't work on the modern battlefield, so I'll respond to this and this.

You don't even understand what AI wrote for you.

Any further discussion will be billed at my hourly rate.

  1. You don't know what you're talking about
  2. You don't know what your AI has written because you don't understand that either.

1

u/cryptopindar 20d ago

Alright, I concede. Thanks for your time and insights! Unfortunately, I don’t think I can afford your hourly rate. 😂 Cheers!

2

u/cryptopindar 20d ago

Perhaps you’re too focused on my use of AI rather than the actual technical argument. I’m starting to wonder if you misunderstood the project performance metrics I’m questioning. Again, what specific statement is factually incorrect?

2

u/pmpdaddyio IT 20d ago

Can a project report excellent EVM indicators while its critical path is deteriorating, productivity is declining, and its forecast completion date is slipping? Absolutely.

No, it can't. It is literally the driver of the critical path reporting. If your critical path is "deteriorating", i.e. tasks are slipping and moving out of the CP, your SPI will adjust accordingly.

Indirectly, and typically, if tasks are slipping, there is an impact on cost. Perhaps it's resource extension, or the addition of rework, non-managed changed, etc., your Cost performance index will adjust accordingly as well.

This also pushes your estimate to completion from a cost and time standpoint.

So, how are you claiming EVM does not indicate the true health of a project? I don't think you are truly using it if you think that.

A healthy SPI 

Here is your first misnomer. There is no such thing as a healthy SPI. You are either on schedule, ahead of schedule, or behind schedule. At the time of measurement. These do not indicate health; they are simply ratios. A project ahead of schedule (which you seem to factor as healthy) is just as bad as one behind schedule, as you will run into standing army costs.

A favorable CPI doesn’t necessarily mean the final margin is protected.

Your next misnomer. There is no favorable CPI. You are either on budget, over, or under, again at the time of measurement. You are again looking at the value in isolation. I might need to spend significantly early in the project to mitigate a risk and build out my savings later (maybe make a huge hardware buy to get vendor savings). This is why the ETC value is so important, yet you fail to include it.

placing greater emphasis on schedule integrity, critical path movement, productivity, forecast reliability, and actual completion risk.

You mean using actual EVM and not just pulling one or two isolated values out of the effort? I agree. Your examples do not take into the full value of EVM.

2

u/cryptopindar 20d ago

I think you're actually reinforcing my argument.

You're describing how EVM should be used within a comprehensive project controls framework. I'm questioning whether traditional EVM indicators are sufficient to represent actual project health.

Let's take a simple example.

Suppose a project has 100 activities. Most noncritical activities are progressing ahead of plan, generating substantial earned value. Meanwhile, a handful of activities on the driving critical path are delayed, pushing the forecast completion date back by 30 days.

Your SPI can still be above 1.0 because SPI = EV / PV. It is weighted by budgeted value, not by the activities governing project completion.

Where in that equation does critical-path deterioration automatically translate into a proportional SPI adjustment?

That's precisely the distinction I'm making.

And yes, ETC and EAC are important. But they're forecasts dependent on assumptions, remaining work, and the quality of the underlying data. They don't independently establish whether the schedule is logically achievable.

I'm not arguing that EVM is useless. I'm arguing that financially weighted progress measurement should not be mistaken for schedule-network integrity or completion-date confidence.

We can have excellent earned value metrics and still have a deteriorating critical path. Those two conditions are mathematically compatible.

Perhaps the bigger question isn't whether we're using EVM correctly, but whether we've become too dependent on it as the primary indicator of project health.

1

u/pmpdaddyio IT 20d ago

You're describing how EVM should be used within a comprehensive project controls framework. I'm questioning whether traditional EVM indicators are sufficient to represent actual project health.

So you are stating that when EVM isn't used properly it doesn't work? Hmmm. Gee, go figure captain obvious.

Where in that equation does critical-path deterioration automatically translate into a proportional SPI adjustment?

It doesn't because that is not how EVM works. you are isolating the ratios. Yu can run an SPI on the critical path tasks only, or do it on both. In MS Project for instance, there is a view where you can look at CPI/SPI in relation to the critical path. I use it all the time.

And yes, ETC and EAC are important. But they're forecasts dependent on assumptions, remaining work, and the quality of the underlying data. They don't independently establish whether the schedule is logically achievable.

Given an established methodology, and assuming you understand the full concept, (and I am not seeing that here), these are not assumptions. They are data driven and adjust regularly. That is why you can rebaseline as often as you need. Projects and schedules are dynamic. You respond accordingly.

We can have excellent earned value metrics and still have a deteriorating critical path. Those two conditions are mathematically compatible.

Absolutely, if you are managing the project poorly. I use a multitude of values to actively manage my project. EVM is a great tool and provides me with a majority of what I need but I don't collect non relevant voodoo data. It is used as supplemental info.

You seem to think all of this is done in isolation when in fact it is not.

Perhaps the bigger question isn't whether we're using EVM correctly, but whether we've become too dependent on it as the primary indicator of project health.

Well, you are both using it incorrectly, (or limitedly), and it isn't a primary indication of health as I stated a few times.

2

u/cryptopindar 20d ago

Gee, I think we’re getting somewhere. 😄
You just acknowledged that critical-path deterioration doesn’t automatically translate into SPI. That’s precisely my point.
Yes, you can filter critical activities in MS Project and examine their CPI/SPI. But that’s combining earned value analysis with CPM information. The critical-path identification comes from the scheduling engine, not from the earned value equations themselves.
And even an SPI calculated exclusively for critical activities doesn’t quantify the resulting completion delay. You still need to evaluate the remaining durations, logic relationships, calendars, float, and driving paths.
Regarding ETC and EAC being data-driven rather than assumption-based, those aren’t mutually exclusive. A forecast can be based on excellent historical data and still depend on assumptions about future productivity, resource availability, and remaining costs.
Also, I would challenge the suggestion that you can simply rebaseline whenever necessary. Rebaselining may be justified through formal change control, but doing it repeatedly to accommodate performance deterioration risks obscuring the original commitments and historical variance.
I’m not questioning whether EVM is useful. I’m questioning whether its conventional indicators deserve the authority they’re often given in assessing overall project health.
You keep explaining how EVM can be supplemented with other project controls techniques. I agree. That’s exactly why I argue it should not be treated as a standalone measure of project health.
And for what it’s worth, disagreement over methodology doesn’t necessarily mean someone doesn’t understand it. Sometimes it simply means we’re challenging different assumptions.

1

u/pmpdaddyio IT 20d ago

JFC you are dense and I'm trying to be polite here. I think you need to go back and evaluate your knowledge here. I have been running multimillion dollar projects and EVM is a key tool.

1

u/cryptopindar 20d ago

Gee, did I ever say EVM wasn’t a key tool? 😂
We’re managing multimillion-dollar projects too, so let’s not turn this into a competition over project values or years of experience.
I’ve repeatedly acknowledged that EVM is valuable. My argument has always been about its limitations as an indicator of overall project health, particularly when evaluating schedule integrity, critical path deterioration, and completion risk.
You yourself acknowledged that critical path deterioration doesn’t automatically translate into SPI. That’s a mathematical distinction, not a matter of opinion or experience.
And frankly, managing multimillion-dollar projects doesn’t make any methodology immune to criticism. Engineering practices evolve precisely because professionals are willing to question established approaches.
We can disagree on the weight EVM deserves without questioning each other’s competence.
If your position is that EVM is a key tool within a broader project controls framework, then congratulations, we actually agree.
The disagreement seems to be about something I never claimed in the first place.

0

u/pmpdaddyio IT 18d ago

“Earned Value Management (EVM) is overrated, and the industry needs to seriously revisit, reassess, and recalibrate how we use it.”

That was the entirety of your post. Maybe go back and read.

0

u/cryptopindar 18d ago

unpopular opinion

0

u/pmpdaddyio IT 17d ago

Opinions can be grossly misinformed, as this one clearly is.

0

u/cryptopindar 17d ago

i am only responsible to what i say, but not of what you understood.

→ More replies

3

u/Appropriate-Ad-4148 20d ago

Haven't ever conversed on any of these specific terms in Construction Management, outside of discussing the PMP exam.

How's it looking compared to the initial estimate and schedule? Anything we can get ahead of down the line to save some money or speed things up?

"We're on track to hit the margin we anticipated + some fat, albeit a couple a months later than we'd like due to those owner requested changes. We've got that long lead item ordered before those material costs went up, so that's a little pickup for us. Also, the Concrete guys sent a proposal to pickup some more work for that slab outside the building."

I'm not distilling all that down into a meaningless metric for leadership unless they tell me to.

4

u/[deleted] 20d ago

EVM is one of my favorite project dashboarding and reporting tools. It's low hanging fruit that provides visualization to executives who need pretty pictures and graphs.

Don't use it at your own peril.

2

u/PplPrcssPrgrss_Pod IT 20d ago

Agree overall. I see utility in EVM for manufacturing and distribution focused things.

For general project management, some sort of formula or even our soft skills that keep the tribal constraints plus team alignment, communication, change readiness combination is a much better indicator of the value of a project output and predictions.

2

u/yes_thats_right 16d ago

  EVM measures performance against a defined baseline, but it doesn’t necessarily tell us whether the project is truly progressing toward successful completion.

I think “completion” is the key to this discussion.

From an old school waterfall perspective, a project is complete when all milestones have been hit and you have run out of tasks on your project plan.

I haven’t seen a project that operates this way in many years.

Nowdays, with agile and product management being so popular, projects are completed when the primary goals have been achieved, ROI starts to deteriorate, and other projects become high priority. All of this requires an understanding of value achieved and remaining. EVM as a concept, helps to determine how much value we have achieved and at what cost, which helps prioritize future investment in this project.

I don’t think the methodology needs to be as rigid as PMP would recommend, but the principles remain useful.

1

u/One-Light-8453 19d ago

nah, I don't think EVM is the problem, SPI on its own is. it goes to 1.0 at the end no matter how late you finish. earned schedule fixes most of that.

1

u/Adventurous-Hunt4683 20d ago

You give it as much authority as it deserves. The reason Project Managers are embedded with the project team is so they can take the pulse of the project. The speed and quality of reporting often changes a long time before EVM shows a change.

0

u/[deleted] 17d ago

[removed] — view removed comment

1

u/cryptopindar 17d ago

Waterfall usually, you can say fixed scope and or well defined scope

1

u/cryptopindar 17d ago

From my perspective, Waterfall, Agile, Scrum, and Sprints are simply different approaches to organizing and delivering work. The fundamentals of project management remain the same.