r/projectmanagement • u/cryptopindar • 20d ago
EVM
Unpopular opinion: Earned Value Management (EVM) is overrated, and the industry needs to seriously revisit, reassess, and recalibrate how we use it.
We have become obsessed with CPI, SPI, and earned value percentages, as though they reliably reflect actual project health.
But here’s the uncomfortable question: Can a project report excellent EVM indicators while its critical path is deteriorating, productivity is declining, and its forecast completion date is slipping? Absolutely.
EVM measures performance against a defined baseline, but it doesn’t necessarily tell us whether the project is truly progressing toward successful completion.
A healthy SPI doesn’t guarantee an achievable completion date. A favorable CPI doesn’t necessarily mean the final margin is protected.
Perhaps it’s time we stopped treating EVM as the gold standard of project performance and started placing greater emphasis on schedule integrity, critical path movement, productivity, forecast reliability, and actual completion risk.
My question to fellow planners and project controls professionals: Are we measuring project performance, or are we simply measuring how well our reporting formulas look?
EVM still has value. But perhaps we’ve given it far more authority than it deserves.
4
u/cryptopindar 20d ago
Sorry if I offended anyone here. That was never my intention. Just sharing thoughts and encouraging some healthy debate. We may disagree on methodologies, but at the end of the day, we’re all professionals learning from each other. No hard feelings. Love you guys! 😂❤️🍻
2
u/SVAuspicious Confirmed 20d ago
No. If you're seeing that you're doing something wrong. Most often the work that's actually being done is not what is in the baseline and people are reporting as best they can because 1. they have to and 2. they don't understand the implications.
Your formatting suggests AI. Even if you wrote it yourself, perhaps you've become too dependent on software and have lost sight of actual methodology.
If you have a project off track as you describe and it is not reflected in CPI and SPI it's you and the project, not EVM. I've found that (context: turnaround PM, I walk into dumpster fires on purpose) one easy way to identify that is to calculate and graph EVM CPI and SPI at the task level or one level up in the WBS (depending on task size) and look at variation (just look at the graph - no additional calculations). If it's all over the place from very low to very high that's an indication your baseline doesn't reflect work that is actually being done. Another indicator is not collecting individual timesheets. Management estimates based on assignments are not good enough for anything much less EVM.
"You're off the reservation, mate."
2
u/pmpdaddyio IT 20d ago
No, it can't. It is literally the driver of the critical path reporting. If your critical path is "deteriorating", i.e. tasks are slipping and moving out of the CP, your SPI will adjust accordingly.
Indirectly, and typically, if tasks are slipping, there is an impact on cost. Perhaps it's resource extension, or the addition of rework, non-managed changed, etc., your Cost performance index will adjust accordingly as well.
This also pushes your estimate to completion from a cost and time standpoint.
So, how are you claiming EVM does not indicate the true health of a project? I don't think you are truly using it if you think that.
Here is your first misnomer. There is no such thing as a healthy SPI. You are either on schedule, ahead of schedule, or behind schedule. At the time of measurement. These do not indicate health; they are simply ratios. A project ahead of schedule (which you seem to factor as healthy) is just as bad as one behind schedule, as you will run into standing army costs.
Your next misnomer. There is no favorable CPI. You are either on budget, over, or under, again at the time of measurement. You are again looking at the value in isolation. I might need to spend significantly early in the project to mitigate a risk and build out my savings later (maybe make a huge hardware buy to get vendor savings). This is why the ETC value is so important, yet you fail to include it.
You mean using actual EVM and not just pulling one or two isolated values out of the effort? I agree. Your examples do not take into the full value of EVM.
3
u/Appropriate-Ad-4148 20d ago
Haven't ever conversed on any of these specific terms in Construction Management, outside of discussing the PMP exam.
How's it looking compared to the initial estimate and schedule? Anything we can get ahead of down the line to save some money or speed things up?
"We're on track to hit the margin we anticipated + some fat, albeit a couple a months later than we'd like due to those owner requested changes. We've got that long lead item ordered before those material costs went up, so that's a little pickup for us. Also, the Concrete guys sent a proposal to pickup some more work for that slab outside the building."
I'm not distilling all that down into a meaningless metric for leadership unless they tell me to.
4
u/[deleted] 20d ago
EVM is one of my favorite project dashboarding and reporting tools. It's low hanging fruit that provides visualization to executives who need pretty pictures and graphs.
Don't use it at your own peril.
2
u/PplPrcssPrgrss_Pod IT 20d ago
Agree overall. I see utility in EVM for manufacturing and distribution focused things.
For general project management, some sort of formula or even our soft skills that keep the tribal constraints plus team alignment, communication, change readiness combination is a much better indicator of the value of a project output and predictions.
2
u/yes_thats_right 16d ago
I think “completion” is the key to this discussion.
From an old school waterfall perspective, a project is complete when all milestones have been hit and you have run out of tasks on your project plan.
I haven’t seen a project that operates this way in many years.
Nowdays, with agile and product management being so popular, projects are completed when the primary goals have been achieved, ROI starts to deteriorate, and other projects become high priority. All of this requires an understanding of value achieved and remaining. EVM as a concept, helps to determine how much value we have achieved and at what cost, which helps prioritize future investment in this project.
I don’t think the methodology needs to be as rigid as PMP would recommend, but the principles remain useful.
1
u/One-Light-8453 19d ago
nah, I don't think EVM is the problem, SPI on its own is. it goes to 1.0 at the end no matter how late you finish. earned schedule fixes most of that.
1
u/Adventurous-Hunt4683 20d ago
You give it as much authority as it deserves. The reason Project Managers are embedded with the project team is so they can take the pulse of the project. The speed and quality of reporting often changes a long time before EVM shows a change.
0