r/surat • u/Lucky_Association992 • 4h ago
AskSurat Surat Metro: kya pohchya, kyare chalu thase?
First stretch is Dream City to Althan Tenement. 8.5 km, 7 stations: Dream City, Convention Centre, Bhimrad, Women ITI, VIP Road, Althan Gam, Althan Tenement. Trials chalu che since 29 March 2026.
Safety clearance (RDSO and CMRS) baki che. Ticket tyar j vechase jyare te aavse.
We were told Diwali or November end. Diwali to nikli gai, and no official date yet. I'd call it a hope, not a promise.
Full network is about 40 km with 38 stations. Most estimates say December 2027.
The project has already missed Dec 2023, Dec 2024 and June 2025. So ghare thi nikli ne "aaje metro ma jaiye" na karta, lol.
Koi ne official date khabar hoy to kaho.