ERCOT & Grid ERCOT is taking a closer look at the growth of medium-sized electricity loads across Texas.
On October 26, ERCOT sent requests to 132 transmission and distribution utilities asking for information on interconnection requests ranging from 10 MW to under 75 MW.
The reason is straightforward: these projects are growing, and ERCOT wants a better understanding of how much capacity they're requesting, where they're located, and when they expect to come online.
ERCOT's preliminary November data identified roughly 11 GW of requested capacity from medium loads. More than 85% of that capacity came from projects above 50 MW.
That's a considerable amount of demand sitting below the threshold ERCOT uses to classify large loads.
The bigger question is how this growth interacts with existing grid capacity, transmission planning and other incoming developments across Texas.
It's another reminder that grid growth isn't limited to hyperscale data centers. A lot of projects in the 10–75 MW range can collectively create meaningful infrastructure and planning challenges.