r/AskContractors • u/ObiethePitBull • 19h ago
Contractor skipped Wedi sealant on basement shower/other waterproofing concerns. How worried should I be?
Getting a basement bathroom redone and I'm not a tile guy, but some of this doesn't look right to me. Photos attached. Trying to figure out what's a real problem vs me overthinking it before they finish up and I finalize payment. I realize I probably should’ve asked these questions earlier.
Setup is a traditional mud bed pan with a 40 mil PVC liner (Oatey), then Wedi Sentinel Pro board on the walls over it. Liner goes up the wall maybe 6"? Tile is all up now, floor is grouted but not the walls.
Stuff I noticed:
- No Wedi joint sealant on any of the seams or screws. They said they put silicone in the screw holes before screwing, saw no sign of silicone (figured that would leave some residue). Inside corners have some kind of tape and mud, outside corners have nothing.
- Hansgrohe iBox valve. I can't tell if anything is sealing the board to the valve body. Didn't see the black sealing collar on the face of the board. Trim isn't on yet.
- Spout: nothing sealing the hole in the board that I know of
- The liner corners at the curb (where it folds over and down the outside) weren't sealed or taped as far as I can tell.
- The niche looks like it had the inside corners taped, but not outside or top
- They put board on top of the curb and screwed it down, through the liner into the wood. After I said something they put silicone over the screw heads.
- Curb is now capped with a quartz-like piece (2 cut pieces). It's dead level, no slope back into the shower. Glass is going on top of it, door will be on side perpendicular to wall
Questions:
- What do I need to ask them for clarification on?
- With a liner under everything, are the unsealed Wedi seams actually a big deal?
- Should I make them inject sealant around the valve before the trim goes on?
- Screws through the liner on the curb top: how bad is this with a quartz cap over it?
- Level curb with glass on top, is that acceptable?
- Anything else I should ask them to fix or show me before I pay?
Not trying to bash the contractor, just want to know what's worth pushing on. Thanks for any help