Job is a split entry (basement and main floor) added to the house. Originally it had a below ground basement entry (think of a storm cellar llike the Wizard of Oz). Basement wall was deteriorating around it and wanted access to backyard from the house.
The original estimate included concrete block wall on the outside wall of the new entryway. Work was delayed longer than hoped as financing was done through a local city/bank initiative, took forever to get appraisal done to determine loan amount, and so on.
GC wants to switch to wood (below ground) for that wall. I was surprised as we are in an area with heavy clay soil (bottom of ancient lake bed) but it can be done to meet code. He claims going with the original plan would cost $5000 more but only explanation is that it could have been done that way in July and now "we're out of time" (current temps are 20 low to 35-ish high)
Text:
GC: This job was estimated to be done in July not October November. That’s the biggest problem. We’re out of time for the weather here.
To GC: Can you explain how the weather is affecting the costs to that extent? We have an infrared heater, and concrete was poured today
GC:Yes, and we covered it with an insulated tarp so it doesn’t freeze (Then makes a pitch because he wants to get materials tomorrow AM)
to GC: Still would like to understand specifically how the weather affects the estimated cost. Curing slower but enough to make it $5k more expensive?
GC: This is our timeline. There’s no extra charge if we do can do it this way. If you wanted the job done, it should’ve been done in July like we Bid it. Thank you--Mxxxxxx
Can anyone explain how to understand this?