After reading a few posts on here regarding waits for various aspects of the Solar process, I thought I'd post my success story...
1st oct, a nice man came round and quoted me for 10 * Aiko 490W, 1 * 9.Sigen Battery 9.04kWh, 1 * Sigen Controller / Inverter 6kW, 2 * Scaffolding, all the bits and a promise of taking care of everything.
I checked the numbers, they were there or there abouts for my region (hertfordshire) but I really liked the company's ethos and attitude, so that and a quick check of other people's experiences on reddit with them and I confirmed on the 5th of October that I wished to proceed.
6th of Oct, the installer put my application in with my DNO (UK Power Networks) for G99.
6th Oct PM I got an email from my installer confirming that the application had be approved.
15th Oct my installer confirmed my install date to be 2nd Nov.
30th Oct, scaffolding went up.
2nd Nov installation happened, all very smooth - arrived at 9:30am coinciding with the delivery of all the kit. Finished up at 5pm. Very neat and tidy (things like digging up gravel to lay the cables underneath and replacing it all, which I didn't even notice until they'd gone). Was demonstrated (so I could video it) how I could use the clamps to swap the EV charger (OHME) from blind or visible to the Sigen system.
I was on Octopus, standard tariff, so on the 3rd Nov I swapped to Intelligent Go and started charging my house battery up on cheap rate, and as predicted, there was enough in the battery to last a normal use day. It's closer than I'd like, I'd rather have a bit more storage but genuinely the cost of larger battery and the ROI wouldn't be there, it would just be more comfortable on totally overcast winter days.
5th Nov my DNO emailed me direct with my export MPAN number for export.
16th Nov my installer send me all the finalised paperwork with the above MPAN and also the MCS certificate so I could apply for export with Octopus.
18th November I applied for an export tariff with Octopus. Did it online at https://octopus.energy/smart/outgoing/ where it just recognised my above MCS certificate number.
today 21st November, Octopus have activated my export tariff (I can already see the section in the app) and so far today I've exported 2kWh to the grid so made back a grand total of 26pence :-D
So from quote to fully exporting to the grid and being paid has been 50 days, which could be some sort of record? Overall, been a really good experience and I've also been surprised at how much I'm generating during November. Overall, for me, this wasn't about ROI but being slightly nicer to the environment and more aware of my energy use.